Sanctuary Rooms Build Team 主堂房间建堂招募
Week 2: a smaller, role-based crew led by Ron; see the live schedule for dates and confirmed assignments. 第二周采用荣强带领的小团队,日期及已确认分工请查看最新排班。
Help Us Build the Sanctuary Rooms
Current plan: October installation schedule and crew roster. Week 2 is planned for Tuesday–Friday, October 13–16. Tuesday starts at 5:30 pm; other times and daily attendance are being confirmed.
Week 2 uses three build helpers alongside Ron: one cutting, one pre-drilling, and one assisting with fastening/installation. About two or three practical-support volunteers may help separately, as needed.
Status: Tuesday still needs one installation helper; later evenings and support are being confirmed. See the live schedule for daily roles and gaps.
Last updated: October 12, 2026.
In Short
Ron leads work on the two sanctuary rooms. First strengthen the framing and connections, then install the stained exterior-facing boards and progress door work as feasible. Interior boards/drywall, surface finishing and painting follow electrical work. Electrical timing is outside Ron’s direct control.
Ron estimated roughly two more weeks overall, including about a week after electrical work finishes. This is a working estimate, not a completion commitment. Adam and Gabriel are confirmed for Tuesday cutting/pre-drilling, with the split assigned by Ron; later attendance is not implied.
Who We Are Looking For
- Role-based construction help: Cutting to Ron’s measurements, pre-drilling, and fastening/installation assistance. Ron measures, directs the work, makes decisions and handles fastening where his experience keeps the work moving. Roles can flex by task.
- Separate practical support: Moving suitable materials, tidying, cleanup and encouragement. These roles do not count toward the three construction positions. Light-duty volunteers must not lift heavy items.
- Careful on site: Follow Ron’s instructions and work within your ability. Ron can guide/train suitable helpers; cutting requires his assignment.
- Voluntary participation and rotation: Everyone is welcome to take part, even when a shift is covered; tasks are assigned by Ron. Tell us the actual dates and times you can help. No one is expected to attend every evening.
The Commitment
- Dates: Tuesday–Friday, October 13–16. Tuesday starts at 5:30 pm; finish time and other evenings’ times are to be confirmed. See the live schedule rather than assuming last week’s hours.
- Break: No construction on October 11–12. Sunday, October 18, is a rest day.
- Friday cleanup: Prepare for Saturday’s Cantonese worship and 5L2F. Construction cutoff and cleanup attendance are still to be confirmed. Retain floor protection unless a change is agreed.
- Saturday: No construction shift is scheduled; any work needs separate coordination around church activities.
Youth Scripture-writing Opportunity
Ron agreed in principle to Scripture being written with markers on approved interior framing before it is covered, with photos as a record. Timing and surfaces must be coordinated with Ron. Young people must be supervised in a safe area separate from hazardous work; no activity time is booked yet.
What You Do Not Need
- You do not need to be a professional builder or carpenter.
- You do not need your own tools.
- You do not need to have been part of the design or feedback process.
How to Sign Up
Please let Thian-Peng know which dates and times you can help, your tool experience, and whether you prefer a construction or support role. Daily attendance and building access are confirmed separately; the live schedule is the source for confirmed assignments.
Background
For what the rooms are, why we are building them, and what the congregation asked for, see Sanctuary Rooms: What We're Building and What We Need From You.
招募弟兄姊妹参与主堂房间施工
最新安排:十月安装排班及每日帮手名单。第二周计划于 10 月 13 日至 16 日(周二至周五)施工。周二晚上 5:30 开始;其他时间及每天出席仍在确认中。
第二周采用较小团队:除荣强以外,3 位施工帮手,分别切板、预钻孔及协助固定/安装。另按需要安排约 2–3 位实际支援人员。
状态:周二还需 1 位固定/安装帮手;其余晚上及支援正在确认中。每天岗位和缺口请查看最新排班。
最后更新:2026 年 10 月 12 日。
简要说明
荣强带领主堂两间房间的施工。先加强框架及连接,再安装已刷好的外侧木板,并按进度处理门的工作。电工完成后,再进行内侧板材/石膏板、表面处理及油漆。电工时间不由荣强直接掌握。
荣强估计整体可能还需约两周,其中电工完成后约需一周收尾。这是估计,不是完工承诺。Adam 和 Gabriel 已确认周二协助切板/预钻孔,具体分配由荣强安排;不代表已确认其余日期。
我们需要什么样的帮手
- 按岗位配搭施工:按荣强量好的尺寸切板、预钻孔、协助固定/安装。荣强量尺寸、指挥、作决定,并在需要时亲自固定提高效率;岗位可随工作调整。
- 实际支援另计:搬运合适的材料、整理、清洁及鼓励团队,不计入 3 个施工岗位。轻量支援人员不搬重物。
- 注意现场安全:按荣强指示,在自己能力范围内做工;他可指导和培训合适的帮手,切板须由他安排。
- 自愿参与、轮替休息:即使当晚人手已齐,愿意参与仍然欢迎,具体工作由荣强安排。请告诉我们实际方便的日期和时间,不需要每晚都来。
时间安排
- 日期:10 月 13 日至 16 日(周二至周五)。周二晚上 5:30 开始;结束时间和其余晚上的时间待确认。请以最新排班为准,不自动沿用上周时段。
- 休息:10 月 11、12 日不施工;10 月 18 日(主日)休息。
- 周五清洁:为周六粤语崇拜及五饼二鱼预备。停止施工时间和清洁人手待确认。地板保护继续保留,除非另有商定。
- 周六:尚未安排施工,如需做工须另行协调教会活动。
年轻人写经文的机会
荣强原则上同意在内侧框架封板前,用记号笔在获准的位置写经文,并拍照留念。时间和位置须与荣强协调。年轻人须有人带领,在与危险施工分开的安全区域进行;活动时间尚未安排。
你不需要具备的
- 不需要是专业建筑或木工师傅。
- 不需要自备工具。
- 不需要曾参与设计或意见收集。
如何报名
请告诉天平你方便的日期和时间、使用工具的经验,以及想参与施工还是支援。逐日出席及开门安排分开确认;已确认分工以最新排班为准。
背景资料
关于这两间房间是什么、为什么要建、以及会众提出了哪些需要,请参阅主堂房间:我们要建什么,需要你回应什么。
招募弟兄姊妹參與主堂房間施工
最新安排:十月安裝排班及每日幫手名單。第二週計劃於 10 月 13 日至 16 日(週二至週五)施工。週二晚上 5:30 開始;其他時間及每天出席仍在確認中。
第二週採用較小團隊:除榮強以外,3 位施工幫手,分別切板、預鑽孔及協助固定/安裝。另按需要安排約 2–3 位實際支援人員。
狀態:週二還需 1 位固定/安裝幫手;其餘晚上及支援正在確認中。每天崗位和缺口請查看最新排班。
最後更新:2026 年 10 月 12 日。
簡要説明
榮強帶領主堂兩間房間的施工。先加強框架及連接,再安裝已刷好的外側木板,並按進度處理門的工作。電工完成後,再進行內側板材/石膏板、表面處理及油漆。電工時間不由榮強直接掌握。
榮強估計整體可能還需約兩週,其中電工完成後約需一週收尾。這是估計,不是完工承諾。Adam 和 Gabriel 已確認週二協助切板/預鑽孔,具體分配由榮強安排;不代表已確認其餘日期。
我們需要什麼樣的幫手
- 按崗位配搭施工:按榮強量好的尺寸切板、預鑽孔、協助固定/安裝。榮強量尺寸、指揮、作決定,並在需要時親自固定提高效率;崗位可隨工作調整。
- 實際支援另計:搬運合適的材料、整理、清潔及鼓勵團隊,不計入 3 個施工崗位。輕量支援人員不搬重物。
- 注意現場安全:按榮強指示,在自己能力範圍內做工;他可指導和培訓合適的幫手,切板須由他安排。
- 自願參與、輪替休息:即使當晚人手已齊,願意參與仍然歡迎,具體工作由榮強安排。請告訴我們實際方便的日期和時間,不需要每晚都來。
時間安排
- 日期:10 月 13 日至 16 日(週二至週五)。週二晚上 5:30 開始;結束時間和其餘晚上的時間待確認。請以最新排班為準,不自動沿用上週時段。
- 休息:10 月 11、12 日不施工;10 月 18 日(主日)休息。
- 週五清潔:為週六粵語崇拜及五餅二魚預備。停止施工時間和清潔人手待確認。地板保護繼續保留,除非另有商定。
- 週六:尚未安排施工,如需做工須另行協調教會活動。
年輕人寫經文的機會
榮強原則上同意在內側框架封板前,用記號筆在獲准的位置寫經文,並拍照留念。時間和位置須與榮強協調。年輕人須有人帶領,在與危險施工分開的安全區域進行;活動時間尚未安排。
你不需要具備的
- 不需要是專業建築或木工師傅。
- 不需要自備工具。
- 不需要曾參與設計或意見收集。
如何報名
請告訴天平你方便的日期和時間、使用工具的經驗,以及想參與施工還是支援。逐日出席及開門安排分開確認;已確認分工以最新排班為準。
背景資料
關於這兩間房間是什麼、為什麼要建、以及會眾提出了哪些需要,請參閱主堂房間:我們要建什麼,需要你回應什麼。