Week 2: a smaller, role-based crew led by Ron; see the live schedule for dates and confirmed assignments. 第二周采用荣强带领的小团队,日期及已确认分工请查看最新排班。

Help Us Build the Sanctuary Rooms

Current plan: October installation schedule and crew roster. Week 2 is planned for Tuesday–Friday, October 13–16. Tuesday starts at 5:30 pm; other times and daily attendance are being confirmed.

Week 2 uses three build helpers alongside Ron: one cutting, one pre-drilling, and one assisting with fastening/installation. About two or three practical-support volunteers may help separately, as needed.

Status: Tuesday is covered, with on-site support confirmed. Thursday needs two build helpers; Wednesday and Friday each need three. See the live schedule for daily roles and support assignments.
Last updated: October 12, 2026.


In Short

Ron leads work on the two sanctuary rooms. First strengthen the framing and connections, then install the stained exterior-facing boards and progress door work as feasible. Interior boards/drywall, surface finishing and painting follow electrical work. Electrical timing is outside Ron’s direct control.

Ron estimated roughly two more weeks overall, including about a week after electrical work finishes. This is a working estimate, not a completion commitment. On Tuesday, Adam and Gabriel help with cutting/pre-drilling, with the split assigned by Ron; Ken Fong (嘉辉) assists Ron with installation. Judy and Janet provide on-site support, and Judy brings a dish. Du Jiakun is confirmed for cutting on Thursday, October 15. Only the listed dates are confirmed.

Who We Are Looking For

  • Role-based construction help: Cutting to Ron’s measurements, pre-drilling, and fastening/installation assistance. Ron measures, directs the work, makes decisions and handles fastening where his experience keeps the work moving. Roles can flex by task.
  • Separate practical support: Moving suitable materials, tidying, cleanup and encouragement. These roles do not count toward the three construction positions. Light-duty volunteers must not lift heavy items.
  • Careful on site: Follow Ron’s instructions and work within your ability. Ron can guide/train suitable helpers; cutting requires his assignment.
  • Voluntary participation and rotation: Everyone is welcome to take part, even when a shift is covered; tasks are assigned by Ron. Tell us the actual dates and times you can help. No one is expected to attend every evening.

The Commitment

  • Dates: Tuesday–Friday, October 13–16. Tuesday starts at 5:30 pm; finish time and other evenings’ times are to be confirmed. See the live schedule rather than assuming last week’s hours.
  • Break: No construction on October 11–12. Sunday, October 18, is a rest day.
  • Friday cleanup: Prepare for Saturday’s Cantonese worship and 5L2F. Construction cutoff and cleanup attendance are still to be confirmed. Retain floor protection unless a change is agreed.
  • Saturday: No construction shift is scheduled; any work needs separate coordination around church activities.

Youth Scripture-writing Opportunity

Ron agreed in principle to Scripture being written with markers on approved interior framing before it is covered, with photos as a record. Timing and surfaces must be coordinated with Ron. Young people must be supervised in a safe area separate from hazardous work; no activity time is booked yet.

What You Do Not Need

  • You do not need to be a professional builder or carpenter.
  • You do not need your own tools.
  • You do not need to have been part of the design or feedback process.

How to Sign Up

PleaseChoose letan open role from the live schedule and contact Thian-Peng knowwith whichthe datesdate, role and times you can help,help (for example, “Thursday — pre-drilling”). Construction roles are cutting, pre-drilling and installation. Support roles include materials/on-site organization and cleanup, especially Friday’s reset for Saturday activities. Let us know your tool experience,experience or lifting restrictions; Ron confirms suitable assignments and whetherprovides you prefer a construction or support role.guidance. Daily attendance and building access are confirmed separately; the live schedule is the source for confirmed assignments.

Background

For what the rooms are, why we are building them, and what the congregation asked for, see Sanctuary Rooms: What We're Building and What We Need From You.

招募弟兄姊妹参与主堂房间施工

最新安排:十月安装排班及每日帮手名单。第二周计划于 10 月 13 日至 16 日(周二至周五)施工。周二晚上 5:30 开始;其他时间及每天出席仍在确认中。

第二周采用较小团队:除荣强以外,3 位施工帮手,分别切板、预钻孔及协助固定/安装。另按需要安排约 2–3 位实际支援人员。

状态:周二人手已齐,现场支援已确认。周四还需 2 位施工帮手;周三和周五每天还需 3 位。每天岗位及支援请查看最新排班。
最后更新:2026 年 10 月 12 日。


简要说明

荣强带领主堂两间房间的施工。先加强框架及连接,再安装已刷好的外侧木板,并按进度处理门的工作。电工完成后,再进行内侧板材/石膏板、表面处理及油漆。电工时间不由荣强直接掌握。

荣强估计整体可能还需约两周,其中电工完成后约需一周收尾。这是估计,不是完工承诺。周二由 Adam 和 Gabriel 协助切板/预钻孔,具体分配由荣强安排;Ken Fong(嘉辉)协助荣强安装。Judy 和 Janet 现场支援,Judy 带一道菜。Du Jiakun(杜弟兄)已确认 10 月 15 日(周四)切板。只确认所列日期。

我们需要什么样的帮手

  • 按岗位配搭施工:按荣强量好的尺寸切板、预钻孔、协助固定/安装。荣强量尺寸、指挥、作决定,并在需要时亲自固定提高效率;岗位可随工作调整。
  • 实际支援另计:搬运合适的材料、整理、清洁及鼓励团队,不计入 3 个施工岗位。轻量支援人员不搬重物。
  • 注意现场安全:按荣强指示,在自己能力范围内做工;他可指导和培训合适的帮手,切板须由他安排。
  • 自愿参与、轮替休息:即使当晚人手已齐,愿意参与仍然欢迎,具体工作由荣强安排。请告诉我们实际方便的日期和时间,不需要每晚都来。

时间安排

  • 日期:10 月 13 日至 16 日(周二至周五)。周二晚上 5:30 开始;结束时间和其余晚上的时间待确认。请以最新排班为准,不自动沿用上周时段。
  • 休息:10 月 11、12 日不施工;10 月 18 日(主日)休息。
  • 周五清洁:为周六粤语崇拜及五饼二鱼预备。停止施工时间和清洁人手待确认。地板保护继续保留,除非另有商定。
  • 周六:尚未安排施工,如需做工须另行协调教会活动。

年轻人写经文的机会

荣强原则上同意在内侧框架封板前,用记号笔在获准的位置写经文,并拍照留念。时间和位置须与荣强协调。年轻人须有人带领,在与危险施工分开的安全区域进行;活动时间尚未安排。

你不需要具备的

  • 不需要是专业建筑或木工师傅。
  • 不需要自备工具。
  • 不需要曾参与设计或意见收集。

如何报名

请告诉天平你方便的日期和时间、使用工具的经验,以及想参与施工还是支援。请从最新排班选择空缺岗位,联系天平并说明日期、岗位和方便的时间,例如“周四——预钻孔”。施工岗位包括切板、预钻孔及安装;支援岗位包括材料搬运/现场整理及清洁,特别是周五为周六活动预备的清洁。请说明使用工具的经验或搬运限制,由荣强确认合适分工并指导。逐日出席及开门安排分开确认;已确认分工以最新排班为准。

背景资料

关于这两间房间是什么、为什么要建、以及会众提出了哪些需要,请参阅主堂房间:我们要建什么,需要你回应什么。

招募弟兄姊妹參與主堂房間施工

最新安排:十月安裝排班及每日幫手名單。第二週計劃於 10 月 13 日至 16 日(週二至週五)施工。週二晚上 5:30 開始;其他時間及每天出席仍在確認中。

第二週採用較小團隊:除榮強以外,3 位施工幫手,分別切板、預鑽孔及協助固定/安裝。另按需要安排約 2–3 位實際支援人員。

狀態:週二人手已齊,現場支援已確認。週四還需 2 位施工幫手;週三和週五每天還需 3 位。每天崗位及支援請查看最新排班。
最後更新:2026 年 10 月 12 日。


簡要説明

榮強帶領主堂兩間房間的施工。先加強框架及連接,再安裝已刷好的外側木板,並按進度處理門的工作。電工完成後,再進行內側板材/石膏板、表面處理及油漆。電工時間不由榮強直接掌握。

榮強估計整體可能還需約兩週,其中電工完成後約需一週收尾。這是估計,不是完工承諾。週二由 Adam 和 Gabriel 協助切板/預鑽孔,具體分配由榮強安排;Ken Fong(嘉輝)協助榮強安裝。Judy 和 Janet 現場支援,Judy 帶一道菜。Du Jiakun(杜弟兄)已確認 10 月 15 日(週四)切板。只確認所列日期。

我們需要什麼樣的幫手

  • 按崗位配搭施工:按榮強量好的尺寸切板、預鑽孔、協助固定/安裝。榮強量尺寸、指揮、作決定,並在需要時親自固定提高效率;崗位可隨工作調整。
  • 實際支援另計:搬運合適的材料、整理、清潔及鼓勵團隊,不計入 3 個施工崗位。輕量支援人員不搬重物。
  • 注意現場安全:按榮強指示,在自己能力範圍內做工;他可指導和培訓合適的幫手,切板須由他安排。
  • 自願參與、輪替休息:即使當晚人手已齊,願意參與仍然歡迎,具體工作由榮強安排。請告訴我們實際方便的日期和時間,不需要每晚都來。

時間安排

  • 日期:10 月 13 日至 16 日(週二至週五)。週二晚上 5:30 開始;結束時間和其餘晚上的時間待確認。請以最新排班為準,不自動沿用上週時段。
  • 休息:10 月 11、12 日不施工;10 月 18 日(主日)休息。
  • 週五清潔:為週六粵語崇拜及五餅二魚預備。停止施工時間和清潔人手待確認。地板保護繼續保留,除非另有商定。
  • 週六:尚未安排施工,如需做工須另行協調教會活動。

年輕人寫經文的機會

榮強原則上同意在內側框架封板前,用記號筆在獲准的位置寫經文,並拍照留念。時間和位置須與榮強協調。年輕人須有人帶領,在與危險施工分開的安全區域進行;活動時間尚未安排。

你不需要具備的

  • 不需要是專業建築或木工師傅。
  • 不需要自備工具。
  • 不需要曾參與設計或意見收集。

如何報名

請告訴天平你方便的日期和時間、使用工具的經驗,以及想參與施工還是支援。請從最新排班選擇空缺崗位,聯繫天平並説明日期、崗位和方便的時間,例如“週四——預鑽孔”。施工崗位包括切板、預鑽孔及安裝;支援崗位包括材料搬運/現場整理及清潔,特別是週五為週六活動預備的清潔。請説明使用工具的經驗或搬運限制,由榮強確認合適分工並指導。逐日出席及開門安排分開確認;已確認分工以最新排班為準。

背景資料

關於這兩間房間是什麼、為什麼要建、以及會眾提出了哪些需要,請參閱主堂房間:我們要建什麼,需要你回應什麼。