Sanctuary Rooms Build Team 主堂房间建堂招募
Week 3: October 19–23. See the schedule for confirmed helpers and open roles. 第三周:10 月 19–23 日,已确认帮手及空缺岗位请查看排班。
Help Us Build the Sanctuary Rooms
WEEK 3 · OCTOBER 19–23, 2026
Building together, one step at a time.
Monday has two workstreams: George (耀基) focuses on the final wall reinforcement; Brother Ron leads the crew finishing installation of the stained exterior-facing boards. The remaining work moves us toward rooms for parents and small-group gatherings.
Status: George is confirmed for Monday’s wall reinforcement; Brother Du (杜加坤) is confirmed for cutting on Thursday, October 22. 邓集 is confirmed to assist in installation on October 19, 21 and 22, 5:30–9:00 pm each day. Ken Fong (嘉辉) is confirmed as a build helper for Monday, October 19; Ron confirms his task assignment. Adam is confirmed as a build helper Tuesday–Friday, October 20–23; Ron confirms his task assignments. Monday and Thursday’s helper headcounts are covered. George (耀基) is also confirmed as a build helper on Tuesday, October 20, to help with the remaining work; Ron confirms task assignments. Construction openings: Tuesday 2;1; Wednesday 1; Friday 2. Support slots are open separately.
Last updated: October 17, 2026.
Week 3 · helper slots
George is confirmed for Monday’s wall reinforcement; Brother Ron leads the exterior stained-board installation crew. Brother Du (杜加坤) is confirmed for Thursday cutting. 邓集 is confirmed to assist in installation on October 19, 21 and 22, 5:30–9:00 pm each day. Ken Fong (嘉辉) is confirmed as a build helper for Monday, October 19; Ron confirms his task assignment. Adam is confirmed as a build helper Tuesday–Friday, October 20–23; Ron confirms his task assignments. Monday and Thursday’s helper headcounts are covered. George (耀基) is also confirmed as a build helper on Tuesday, October 20, to help with the remaining work; Ron confirms task assignments. Construction openings: Tuesday 2;1; Wednesday 1; Friday 2. Practical-support and food offers are welcome separately. Please use the schedule for the live assignments.
Continue the focused-role model: three construction helpers besides Ron, plus about two or three practical-support people as needed. Ron assigns suitable tasks as the work changes. George fills one of Monday’s construction-helper slots.
Everyone is welcome to take part, even when a shift is covered. Every workday is voluntary; partial evenings and rotation are welcome. Please keep time for family, fellowship and rest.
Progress so far
A record of milestones reached, not a completion percentage. Final wall reinforcement and exterior-board installation are still in progress.
Milestones reached
- Room framing assembledThe basic wood frames are in place; final reinforcement remains.
- Stained boards preparedVolunteers prepared the stained/painted boards now being installed.
- Further connections reinforcedAdditional brackets and stronger wall connections were added in Week 2.
Underway · Monday focus
- Finalize wall reinforcementGeorge returns Monday, October 19, to finish the structural reinforcement to the wall.
- Finish exterior stained boardsBrother Ron leads the crew to finish installing the stained exterior-facing boards.
Still ahead
- Glass windows and doorsInstall the room windows and doors.
- New door openings to the foyerCreate the planned new doorway exits to the foyer.
- Sound insulationInstall sound insulation before closing the walls.
- Drywall and paintHang and finish drywall, then paint.
- Lighting and switchesComplete the lighting and switch installation.
- VentilationInstall ventilation; coordinate power, airflow and the duct route.
- TV and small speakersMount the TV and small speakers for parents and small-group use.
- AV network and wiringComplete the AV/network connections and wiring.
Before closing the walls: Coordinate electrical, AV/network and ventilation routes, then insulation and drywall. Ron confirms the work sequence with the relevant skilled helpers. This is the remaining project scope, not a promise to finish everything in Week 3.
Choose a date. Choose a role.
Contact Thian-Peng (添平) with the date, role and times you can help, plus tool experience or lifting restrictions. Construction and practical support are separate. A signup is confirmed only when it appears in the roster.
You do not need to be a professional builder, own tools, or have been involved in the design. Tell us your experience so suitable work can be assigned.
Glass, electrical, ventilation and structural work need suitable skilled helpers. Open volunteer slots do not authorize specialist tasks. Ron confirms safe assignments; building access is arranged separately.
About 2–3 support people as needed; tasks may be combined. Light-duty support is welcome, with no heavy lifting.
No weekend shift is added here. Any weekend work needs separate confirmation around church activities.
Before each work session
- Confirm that date’s attendance, start/finish times and opening/locking arrangements.
- Ron confirms suitable tasks, tools and the day’s sequence. Coordinate specialist work before closing walls.
- Arrange food and practical support only after confirmation. Light-duty helpers must not lift heavy items.
- Keep floor protection in place unless a change is agreed. Confirm cleanup timing around church activities.
Youth Scripture-writing Opportunity
Ron agreed in principle to Scripture being written with markers on approved interior framing before it is covered, with photos as a record. Timing and surfaces must be coordinated with Ron. Young people must be supervised in a safe area separate from hazardous work; no activity time is booked yet.
Background
For what the rooms are, why we are building them, and what the congregation asked for, see Sanctuary Rooms: What We're Building and What We Need From You.
招募弟兄姊妹参与主堂房间施工
第三周 · 2026 年 10 月 19–23 日
同心建造,一步一步往前。
周一分两项工作:George(耀基)专注完成结构与墙面的加固;荣强弟兄带领团队完成已刷好外侧木板的安装。接下来的工作,让房间逐步为家长及小组聚会预备好。
状态:George 已确认周一参与墙面加固;杜加坤弟兄已确认 10 月 22 日(周四)切板。邓集已确认 10 月 19、21、22 日协助安装,每天 17:30–21:00。Ken(嘉辉)已确认 10 月 19 日(周一)担任施工帮手,具体分工由荣强确认。Adam 已确认 10 月 20–23 日(周二至周五)担任施工帮手,具体分工由荣强确认。周一及周四施工帮手人数已齐。George(耀基)也已确认 10 月 20 日(周二)担任施工帮手,继续协助尚余工作;具体分工由荣强确认。施工空缺:周二 21 位、周三 1 位、周五 2 位。实际支援岗位另计,均可报名。
最后更新:2026 年 10 月 17 日。
第三周 · 帮手报名岗位
George 已确认周一专注完成与墙面的加固;荣强弟兄带领团队安装外侧木板。杜加坤弟兄已确认周四切板。邓集已报名 10 月 19、21、22 日协助安装,每天 17:30–21:00。Ken(嘉辉)已确认 10 月 19 日(周一)担任施工帮手,具体分工由荣强确认。Adam 已确认 10 月 20–23 日(周二至周五)担任施工帮手,具体分工由荣强确认。周一及周四施工帮手人数已齐。George(耀基)也已确认 10 月 20 日(周二)担任施工帮手,继续协助尚余工作;具体分工由荣强确认。施工空缺:周二 21 位、周三 1 位、周五 2 位。实际支援及餐食另行报名;最新分工以排班为准。
沿用按岗位配搭的方式:除荣强以外,3 位施工帮手,另按需要安排约 2–3 位实际支援人员。工作推进时,由荣强安排合适分工。George 占周一其中 1 个施工帮手岗位。
即使当晚人手已齐,愿意参与仍然欢迎。每天参与都是自愿的,可参与部分时段,也可轮替;请顾及家庭、团契及休息。
建设进度一览
按已达到的里程碑记录,不以百分比估算完工程度。与墙面连接的最后加固及外侧木板安装仍在进行中。
已达到的里程碑
- 房间木框架已搭起基本木框架已就位,仍需完成最后加固。
- 外侧木板已刷好弟兄姊妹预备好的木板,已陆续用于安装。
- 已增设连接加固第二周已加装连接件,加强部分结构与墙面的连接。
进行中 · 周一重点
- 完成与墙面的最后加固George(耀基)10 月 19 日(周一)继续完成结构与墙面的加固。
- 完成外侧木板安装由荣强弟兄带领团队,接续已开始的工作,完成已刷好外侧木板的安装。
接下来要完成
- 玻璃窗及门安装房间玻璃窗和门。
- 通往门厅的新门洞开出计划中通往门厅的新门口。
- 隔音材料封墙前放置隔音材料。
- 石膏板及油漆安装石膏板、处理接缝及表面,再上漆。
- 灯具及开关完成照明及开关安装。
- 通风设备安装通风设备,协调电源、气流及风管路线。
- 电视及小音箱为家长及小组使用,安装电视和小音箱。
- 影音网络及布线完成影音、网络连接及相关布线。
封墙前先协调:电线、影音网络及通风路线,再安排隔音材料及石膏板。具体工序由荣强与相关有经验的帮手确认。以上是项目尚余工作,不代表承诺在第三周全部完成。
不需要是专业建造人员,也不需要自备工具或曾参与设计。请说明自己的经验,方便安排合适的工作。
玻璃、电工、通风及结构工作需要合适且有经验的帮手。报名一般施工岗位,不等于可以承担这些工作。由荣强确认安全分工,开门安排另行确认。
按需要合计约 2–3 位,岗位可兼任。欢迎轻量支援,不搬重物。
此处不新增周末施工;如需做工,须另行确认并协调教会活动。
每次开工前
- 逐日确认出席、开始及结束时间,以及开门锁门安排。
- 由荣强确认合适的工作、工具及当天工序;封墙前协调相关专门工作。
- 确认后才安排餐食及实际支援;轻量支援人员不搬重物。
- 地板保护继续保留,除非另有商定;配合教会活动确认清洁时段。
年轻人写经文的机会
荣强原则上同意在内侧框架封板前,用记号笔在获准的位置写经文,并拍照留念。时间和位置须与荣强协调。年轻人须有人带领,在与危险施工分开的安全区域进行;活动时间尚未安排。
背景资料
关于这两间房间是什么、为什么要建、以及会众提出了哪些需要,请参阅主堂房间:我们要建什么,需要你回应什么。
招募弟兄姊妹參與主堂房間施工
第三週 · 2026 年 10 月 19–23 日
同心建造,一步一步往前。
週一分兩項工作:George(耀基)專注完成結構與牆面的加固;榮強弟兄帶領團隊完成已刷好外側木板的安裝。接下來的工作,讓房間逐步為家長及小組聚會預備好。
狀態:George 已確認週一參與牆面加固;杜加坤弟兄已確認 10 月 22 日(週四)切板。鄧集已確認 10 月 19、21、22 日協助安裝,每天 17:30–21:00。Ken(嘉輝)已確認 10 月 19 日(週一)擔任施工幫手,具體分工由榮強確認。Adam 已確認 10 月 20–23 日(週二至週五)擔任施工幫手,具體分工由榮強確認。週一及週四施工幫手人數已齊。George(耀基)也已確認 10 月 20 日(週二)擔任施工幫手,繼續協助尚餘工作;具體分工由榮強確認。施工空缺:週二 21 位、週三 1 位、週五 2 位。實際支援崗位另計,均可報名。
最後更新:2026 年 10 月 17 日。
第三週 · 幫手報名崗位
George 已確認週一專注完成與牆面的加固;榮強弟兄帶領團隊安裝外側木板。杜加坤弟兄已確認週四切板。鄧集已報名 10 月 19、21、22 日協助安裝,每天 17:30–21:00。Ken(嘉輝)已確認 10 月 19 日(週一)擔任施工幫手,具體分工由榮強確認。Adam 已確認 10 月 20–23 日(週二至週五)擔任施工幫手,具體分工由榮強確認。週一及週四施工幫手人數已齊。George(耀基)也已確認 10 月 20 日(週二)擔任施工幫手,繼續協助尚餘工作;具體分工由榮強確認。施工空缺:週二 21 位、週三 1 位、週五 2 位。實際支援及餐食另行報名;最新分工以排班為準。
沿用按崗位配搭的方式:除榮強以外,3 位施工幫手,另按需要安排約 2–3 位實際支援人員。工作推進時,由榮強安排合適分工。George 佔週一其中 1 個施工幫手崗位。
即使當晚人手已齊,願意參與仍然歡迎。每天參與都是自願的,可參與部分時段,也可輪替;請顧及家庭、團契及休息。
建設進度一覽
按已達到的里程碑記錄,不以百分比估算完工程度。與牆面連接的最後加固及外側木板安裝仍在進行中。
已達到的里程碑
- 房間木框架已搭起基本木框架已就位,仍需完成最後加固。
- 外側木板已刷好弟兄姊妹預備好的木板,已陸續用於安裝。
- 已增設連接加固第二週已加裝連接件,加強部分結構與牆面的連接。
進行中 · 週一重點
- 完成與牆面的最後加固George(耀基)10 月 19 日(週一)繼續完成結構與牆面的加固。
- 完成外側木板安裝由榮強弟兄帶領團隊,接續已開始的工作,完成已刷好外側木板的安裝。
接下來要完成
- 玻璃窗及門安裝房間玻璃窗和門。
- 通往門廳的新門洞開出計劃中通往門廳的新門口。
- 隔音材料封牆前放置隔音材料。
- 石膏板及油漆安裝石膏板、處理接縫及表面,再上漆。
- 燈具及開關完成照明及開關安裝。
- 通風設備安裝通風設備,協調電源、氣流及風管路線。
- 電視及小音箱為家長及小組使用,安裝電視和小音箱。
- 影音網絡及佈線完成影音、網絡連接及相關佈線。
封牆前先協調:電線、影音網絡及通風路線,再安排隔音材料及石膏板。具體工序由榮強與相關有經驗的幫手確認。以上是項目尚餘工作,不代表承諾在第三週全部完成。
不需要是專業建造人員,也不需要自備工具或曾參與設計。請説明自己的經驗,方便安排合適的工作。
玻璃、電工、通風及結構工作需要合適且有經驗的幫手。報名一般施工崗位,不等於可以承擔這些工作。由榮強確認安全分工,開門安排另行確認。
按需要合計約 2–3 位,崗位可兼任。歡迎輕量支援,不搬重物。
此處不新增週末施工;如需做工,須另行確認並協調教會活動。
每次開工前
- 逐日確認出席、開始及結束時間,以及開門鎖門安排。
- 由榮強確認合適的工作、工具及當天工序;封牆前協調相關專門工作。
- 確認後才安排餐食及實際支援;輕量支援人員不搬重物。
- 地板保護繼續保留,除非另有商定;配合教會活動確認清潔時段。
年輕人寫經文的機會
榮強原則上同意在內側框架封板前,用記號筆在獲准的位置寫經文,並拍照留念。時間和位置須與榮強協調。年輕人須有人帶領,在與危險施工分開的安全區域進行;活動時間尚未安排。
背景資料
關於這兩間房間是什麼、為什麼要建、以及會眾提出了哪些需要,請參閱主堂房間:我們要建什麼,需要你回應什麼。