Sanctuary Rooms Build Team 主堂房间建堂招募
Week 3: October 19–23. See the schedule for confirmed helpers and open roles. 第三周:10 月 19–23 日,已确认帮手及空缺岗位请查看排班。
Help Us Build the Sanctuary Rooms
WEEK 3 · OCTOBER 19–23, 2026
Building together, one step at a time.
Wall reinforcement, exterior stained boards and ceiling drywall in both rooms are complete. The more difficult second ceiling was finished Wednesday, October 21. Thursday, October 22: install sound insulation and wall drywall under Brother Ron’s direction.
Status: Wall reinforcement and exterior stained-board installation are complete; Brother Du (杜加坤) is confirmed for cutting on Thursday, October 22. 邓集 is confirmed to assist in installation on October 19, 21 and 22, 5:30–9:00 pm each day. Ken Fong (嘉辉) is confirmed as a build helper on Monday, Tuesday, Wednesday and Friday, October 19, 20, 21 and 23; Ron confirms his task assignments. Thursday, October 22 attendance: Adam, Jim Deng (邓集), Brother Du (杜加坤) and Ken Fong (嘉辉) helped with construction. Adam is confirmed as a build helper Tuesday–Friday, October 20–23; Ron confirms his task assignments. Monday through Thursday’s helper headcounts are covered. George (耀基) is also confirmed as a build helper on Tuesday, October 20, to help with the remaining work; Ron confirms task assignments. Gabriel assisted with installation on Tuesday, October 20, and is confirmed to assist again on Wednesday, October 21. Construction openings: Friday 1. Support slots are open separately.
Last updated: October 22, 2026.
Week 3 · helper slots
Wall reinforcement and exterior stained-board installation are complete. Brother Du (杜加坤) is confirmed for Thursday cutting. 邓集 is confirmed to assist in installation on October 19, 21 and 22, 5:30–9:00 pm each day. Ken Fong (嘉辉) is confirmed as a build helper on Monday, Tuesday, Wednesday and Friday, October 19, 20, 21 and 23; Ron confirms his task assignments. Thursday, October 22 attendance: Adam, Jim Deng (邓集), Brother Du (杜加坤) and Ken Fong (嘉辉) helped with construction. Adam is confirmed as a build helper Tuesday–Friday, October 20–23; Ron confirms his task assignments. Monday through Thursday’s helper headcounts are covered. George (耀基) is also confirmed as a build helper on Tuesday, October 20, to help with the remaining work; Ron confirms task assignments. Gabriel assisted with installation on Tuesday, October 20, and is confirmed to assist again on Wednesday, October 21. Construction openings: Friday 1. Practical-support and food offers are welcome separately. Please use the schedule for the live assignments.
Continue the focused-role model: three construction helpers besides Ron, plus about two or three practical-support people as needed. Ron assigns suitable tasks as the work changes. George fills one of Monday’s construction-helper slots.
Everyone is welcome to take part, even when a shift is covered. Every workday is voluntary; partial evenings and rotation are welcome. Please keep time for family, fellowship and rest.
Progress so far
Milestones updated October 21. Both rooms now have ceiling drywall installed. Thursday’s next work is sound insulation and wall drywall; joints, surface finishing and paint remain.
Milestones reached
- Room framing assembledThe basic wood frames are in place.
- Stained boards preparedVolunteers prepared the stained/painted boards; exterior installation is now complete.
- Further connections reinforcedAdditional brackets and stronger wall connections were added in Week 2.
- Wall reinforcement completeFinal reinforcement to the wall is complete.
- Exterior stained boards installedInstallation of the stained exterior-facing boards is complete.
- Both rooms’ ceiling drywall installedFirst room installed October 20; the more difficult second room finished October 21. Drywall joint and surface finishing remain.
- Light switches loweredOctober 21: Alexander addressed George’s suggestion by lowering the light switches for accessibility.
Next · Thursday focus
- Install sound insulationPlanned Thursday, October 22, before wall drywall closes the framing.
- Install wall drywallPlanned Thursday, October 22, after sound insulation; Ron confirms the sequence.
Still ahead
- Glass windows and doorsInstall the room windows and doors.
- New door openings to the foyerCreate the planned new doorway exits to the foyer.
- Drywall and paintBoth ceilings are installed. Wall drywall is planned for Thursday, followed by remaining joint and surface finishing and paint.
- Lighting and switchesLight switches have been lowered to address accessibility height requirements; the remaining lighting and switch work still needs completion.
- VentilationInstall ventilation; coordinate power, airflow and the duct route.
- TV and small speakersMount the TV and small speakers for parents and small-group use.
- AV network and wiringComplete the AV/network connections and wiring.
Before closing the walls: Coordinate electrical, AV/network and ventilation routes, then insulation and drywall. Ron confirms the work sequence with the relevant skilled helpers. This is the remaining project scope, not a promise to finish everything in Week 3.
Choose a date. Choose a role.
Contact Thian-Peng (添平) with the date, role and times you can help, plus tool experience or lifting restrictions. Construction and practical support are separate. A signup is confirmed only when it appears in the roster.
You do not need to be a professional builder, own tools, or have been involved in the design. Tell us your experience so suitable work can be assigned.
Glass, electrical, ventilation and structural work need suitable skilled helpers. Open volunteer slots do not authorize specialist tasks. Ron confirms safe assignments; building access is arranged separately.
About 2–3 support people as needed; tasks may be combined. Light-duty support is welcome, with no heavy lifting.
No weekend shift is added here. Any weekend work needs separate confirmation around church activities.
Before each work session
- Confirm that date’s attendance, start/finish times and opening/locking arrangements.
- Ron confirms suitable tasks, tools and the day’s sequence. Coordinate specialist work before closing walls.
- Arrange food and practical support only after confirmation. Light-duty helpers must not lift heavy items.
- Keep floor protection in place unless a change is agreed. Confirm cleanup timing around church activities.
Youth Scripture-writing Opportunity
Ron agreed in principle to Scripture being written with markers on approved interior framing before it is covered, with photos as a record. Timing and surfaces must be coordinated with Ron. Young people must be supervised in a safe area separate from hazardous work; no activity time is booked yet.
Background
For what the rooms are, why we are building them, and what the congregation asked for, see Sanctuary Rooms: What We're Building and What We Need From You.
招募弟兄姊妹参与主堂房间施工
第三周 · 2026 年 10 月 19–23 日
同心建造,一步一步往前。
墙面最后加固、外侧木板及两间房间的天花板石膏板安装已完成。10 月 21 日(周三)完成较困难的另一间房间天花板。10 月 22 日(周四)由荣强弟兄带领团队安装隔音材料及墙面石膏板。
状态:墙面最后加固及外侧木板安装已完成;杜加坤弟兄已确认 10 月 22 日(周四)切板。邓集已确认 10 月 19、21、22 日协助安装,每天 17:30–21:00。Ken(嘉辉)已确认 10 月 19、20、21、23 日(周一、周二、周三及周五)担任施工帮手,具体分工由荣强确认。10 月 22 日(周四)实际到场帮忙:Adam、Jim Deng(邓集)、杜加坤弟兄及 Ken(嘉辉)。Adam 已确认 10 月 20–23 日(周二至周五)担任施工帮手,具体分工由荣强确认。周一至周四施工帮手人数已齐。George(耀基)也已确认 10 月 20 日(周二)担任施工帮手,继续协助尚余工作;具体分工由荣强确认。Gabriel 10 月 20 日(周二)已参与协助安装,并已确认 10 月 21 日(周三)继续协助。施工空缺:周五 1 位。实际支援岗位另计,均可报名。
最后更新:2026 年 10 月 22 日。
第三周 · 帮手报名岗位
墙面最后加固及外侧木板安装已完成。杜加坤弟兄已确认周四切板。邓集已报名 10 月 19、21、22 日协助安装,每天 17:30–21:00。Ken(嘉辉)已确认 10 月 19、20、21、23 日(周一、周二、周三及周五)担任施工帮手,具体分工由荣强确认。10 月 22 日(周四)实际到场帮忙:Adam、Jim Deng(邓集)、杜加坤弟兄及 Ken(嘉辉)。Adam 已确认 10 月 20–23 日(周二至周五)担任施工帮手,具体分工由荣强确认。周一至周四施工帮手人数已齐。George(耀基)也已确认 10 月 20 日(周二)担任施工帮手,继续协助尚余工作;具体分工由荣强确认。Gabriel 10 月 20 日(周二)已参与协助安装,并已确认 10 月 21 日(周三)继续协助。施工空缺:周五 1 位。实际支援及餐食另行报名;最新分工以排班为准。
沿用按岗位配搭的方式:除荣强以外,3 位施工帮手,另按需要安排约 2–3 位实际支援人员。工作推进时,由荣强安排合适分工。George 占周一其中 1 个施工帮手岗位。
即使当晚人手已齐,愿意参与仍然欢迎。每天参与都是自愿的,可参与部分时段,也可轮替;请顾及家庭、团契及休息。
建设进度一览
10 月 21 日更新:两间房间的天花板石膏板均已安装。周四接着安装隔音材料及墙面石膏板;接缝、表面处理及油漆仍未完成。
已达到的里程碑
- 房间木框架已搭起基本木框架已就位。
- 外侧木板已刷好弟兄姊妹已预备好木板;外侧木板安装现已完成。
- 已增设连接加固第二周已加装连接件,加强部分结构与墙面的连接。
- 墙面最后加固已完成与墙面的最后加固已完成。
- 外侧木板安装已完成已刷好外侧木板的安装已完成。
- 两间房间天花板石膏板均已安装10 月 20 日安装第一间;10 月 21 日完成较困难的另一间。石膏板接缝及表面处理仍未完成。
- 灯光开关已调低10 月 21 日:Alexander 回应 George(耀基)的建议,按无障碍要求调低灯光开关。
下一步 · 周四重点
- 安装隔音材料计划 10 月 22 日(周四)先放置隔音材料,再封墙面石膏板。
- 安装墙面石膏板计划 10 月 22 日(周四)在隔音材料之后安装,由荣强确认工序。
接下来要完成
- 玻璃窗及门安装房间玻璃窗和门。
- 通往门厅的新门洞开出计划中通往门厅的新门口。
- 石膏板及油漆两间天花板石膏板已安装。周四计划安装墙面石膏板,之后仍需处理接缝及表面,再上漆。
- 灯具及开关灯光开关已按无障碍高度要求调低;其余灯具及开关工作仍待完成。
- 通风设备安装通风设备,协调电源、气流及风管路线。
- 电视及小音箱为家长及小组使用,安装电视和小音箱。
- 影音网络及布线完成影音、网络连接及相关布线。
封墙前先协调:电线、影音网络及通风路线,再安排隔音材料及石膏板。具体工序由荣强与相关有经验的帮手确认。以上是项目尚余工作,不代表承诺在第三周全部完成。
不需要是专业建造人员,也不需要自备工具或曾参与设计。请说明自己的经验,方便安排合适的工作。
玻璃、电工、通风及结构工作需要合适且有经验的帮手。报名一般施工岗位,不等于可以承担这些工作。由荣强确认安全分工,开门安排另行确认。
按需要合计约 2–3 位,岗位可兼任。欢迎轻量支援,不搬重物。
此处不新增周末施工;如需做工,须另行确认并协调教会活动。
每次开工前
- 逐日确认出席、开始及结束时间,以及开门锁门安排。
- 由荣强确认合适的工作、工具及当天工序;封墙前协调相关专门工作。
- 确认后才安排餐食及实际支援;轻量支援人员不搬重物。
- 地板保护继续保留,除非另有商定;配合教会活动确认清洁时段。
年轻人写经文的机会
荣强原则上同意在内侧框架封板前,用记号笔在获准的位置写经文,并拍照留念。时间和位置须与荣强协调。年轻人须有人带领,在与危险施工分开的安全区域进行;活动时间尚未安排。
背景资料
关于这两间房间是什么、为什么要建、以及会众提出了哪些需要,请参阅主堂房间:我们要建什么,需要你回应什么。
招募弟兄姊妹參與主堂房間施工
第三週 · 2026 年 10 月 19–23 日
同心建造,一步一步往前。
牆面最後加固、外側木板及兩間房間的天花板石膏板安裝已完成。10 月 21 日(週三)完成較困難的另一間房間天花板。10 月 22 日(週四)由榮強弟兄帶領團隊安裝隔音材料及牆面石膏板。
狀態:牆面最後加固及外側木板安裝已完成;杜加坤弟兄已確認 10 月 22 日(週四)切板。鄧集已確認 10 月 19、21、22 日協助安裝,每天 17:30–21:00。Ken(嘉輝)已確認 10 月 19、20、21、23 日(週一、週二、週三及週五)擔任施工幫手,具體分工由榮強確認。10 月 22 日(週四)實際到場幫忙:Adam、Jim Deng(鄧集)、杜加坤弟兄及 Ken(嘉輝)。Adam 已確認 10 月 20–23 日(週二至週五)擔任施工幫手,具體分工由榮強確認。週一至週四施工幫手人數已齊。George(耀基)也已確認 10 月 20 日(週二)擔任施工幫手,繼續協助尚餘工作;具體分工由榮強確認。Gabriel 10 月 20 日(週二)已參與協助安裝,並已確認 10 月 21 日(週三)繼續協助。施工空缺:週五 1 位。實際支援崗位另計,均可報名。
最後更新:2026 年 10 月 22 日。
第三週 · 幫手報名崗位
牆面最後加固及外側木板安裝已完成。杜加坤弟兄已確認週四切板。鄧集已報名 10 月 19、21、22 日協助安裝,每天 17:30–21:00。Ken(嘉輝)已確認 10 月 19、20、21、23 日(週一、週二、週三及週五)擔任施工幫手,具體分工由榮強確認。10 月 22 日(週四)實際到場幫忙:Adam、Jim Deng(鄧集)、杜加坤弟兄及 Ken(嘉輝)。Adam 已確認 10 月 20–23 日(週二至週五)擔任施工幫手,具體分工由榮強確認。週一至週四施工幫手人數已齊。George(耀基)也已確認 10 月 20 日(週二)擔任施工幫手,繼續協助尚餘工作;具體分工由榮強確認。Gabriel 10 月 20 日(週二)已參與協助安裝,並已確認 10 月 21 日(週三)繼續協助。施工空缺:週五 1 位。實際支援及餐食另行報名;最新分工以排班為準。
沿用按崗位配搭的方式:除榮強以外,3 位施工幫手,另按需要安排約 2–3 位實際支援人員。工作推進時,由榮強安排合適分工。George 佔週一其中 1 個施工幫手崗位。
即使當晚人手已齊,願意參與仍然歡迎。每天參與都是自願的,可參與部分時段,也可輪替;請顧及家庭、團契及休息。
建設進度一覽
10 月 21 日更新:兩間房間的天花板石膏板均已安裝。週四接着安裝隔音材料及牆面石膏板;接縫、表面處理及油漆仍未完成。
已達到的里程碑
- 房間木框架已搭起基本木框架已就位。
- 外側木板已刷好弟兄姊妹已預備好木板;外側木板安裝現已完成。
- 已增設連接加固第二週已加裝連接件,加強部分結構與牆面的連接。
- 牆面最後加固已完成與牆面的最後加固已完成。
- 外側木板安裝已完成已刷好外側木板的安裝已完成。
- 兩間房間天花板石膏板均已安裝10 月 20 日安裝第一間;10 月 21 日完成較困難的另一間。石膏板接縫及表面處理仍未完成。
- 燈光開關已調低10 月 21 日:Alexander 回應 George(耀基)的建議,按無障礙要求調低燈光開關。
下一步 · 週四重點
- 安裝隔音材料計劃 10 月 22 日(週四)先放置隔音材料,再封牆面石膏板。
- 安裝牆面石膏板計劃 10 月 22 日(週四)在隔音材料之後安裝,由榮強確認工序。
接下來要完成
- 玻璃窗及門安裝房間玻璃窗和門。
- 通往門廳的新門洞開出計劃中通往門廳的新門口。
- 石膏板及油漆兩間天花板石膏板已安裝。週四計劃安裝牆面石膏板,之後仍需處理接縫及表面,再上漆。
- 燈具及開關燈光開關已按無障礙高度要求調低;其餘燈具及開關工作仍待完成。
- 通風設備安裝通風設備,協調電源、氣流及風管路線。
- 電視及小音箱為家長及小組使用,安裝電視和小音箱。
- 影音網絡及佈線完成影音、網絡連接及相關佈線。
封牆前先協調:電線、影音網絡及通風路線,再安排隔音材料及石膏板。具體工序由榮強與相關有經驗的幫手確認。以上是項目尚餘工作,不代表承諾在第三週全部完成。
不需要是專業建造人員,也不需要自備工具或曾參與設計。請説明自己的經驗,方便安排合適的工作。
玻璃、電工、通風及結構工作需要合適且有經驗的幫手。報名一般施工崗位,不等於可以承擔這些工作。由榮強確認安全分工,開門安排另行確認。
按需要合計約 2–3 位,崗位可兼任。歡迎輕量支援,不搬重物。
此處不新增週末施工;如需做工,須另行確認並協調教會活動。
每次開工前
- 逐日確認出席、開始及結束時間,以及開門鎖門安排。
- 由榮強確認合適的工作、工具及當天工序;封牆前協調相關專門工作。
- 確認後才安排餐食及實際支援;輕量支援人員不搬重物。
- 地板保護繼續保留,除非另有商定;配合教會活動確認清潔時段。
年輕人寫經文的機會
榮強原則上同意在內側框架封板前,用記號筆在獲准的位置寫經文,並拍照留念。時間和位置須與榮強協調。年輕人須有人帶領,在與危險施工分開的安全區域進行;活動時間尚未安排。
背景資料
關於這兩間房間是什麼、為什麼要建、以及會眾提出了哪些需要,請參閱主堂房間:我們要建什麼,需要你回應什麼。