Sanctuary Rooms Build Team 主堂房间建堂招募
Week 4: October 26–29 placeholders; Thursday cleanup; Friday, October 30 off for rest. 第四周:10 月 26–29 日待确认岗位;周四清洁,10 月 30 日周五休息。
Help Us Build the Sanctuary Rooms
WEEK 4 · OCTOBER 26–30, 2026
Building together, one step at a time.
Sound-insulation panels were installed Friday, October 23, once the right cutting tool was available. Ron led Adam, Ken Fong (嘉辉), Phoenix (小毛) and Phoenix’s dad. Peggy and Ally helped with cleanup; Pastor Kaan prepared a home-style meal for the crew.
Status:Week 4: Roy is confirmed as a construction helper Wednesday and Thursday, October 28 and 29; Qiang Li (李强) is also confirmed Thursday, October 29. Ron assigns suitable tasks. TwoWednesday needs two more construction helpers areand neededThursday onneeds eachone of those days;more; Monday and Tuesday still have three open slots each. Daily work plans, times, other helpers and meal providers remain to be confirmed. Cleanup is needed Thursday, October 29, with helpers and time to confirm. Friday, October 30 is off for rest; no construction or cleanup shift is scheduled.
Last updated: October 24, 2026.
Week 4 · helper slots
Roy is confirmed to help Wednesday and Thursday, October 28 and 29; Qiang Li (李强) is also confirmed Thursday, October 29. Other helpers, meal providers and times remain to be confirmed. Cleanup is Thursday, October 29; Friday, October 30 is off for rest. See the schedule for live assignments.
Week 4 is a placeholder plan: retain the current target of three construction helpers besides Ron, with about 2–3 practical-support people as needed. Daily tasks, times and remaining attendance still need confirmation; no previous-week availability is carried forward.
Everyone is welcome to take part, even when a shift is covered. Participation is voluntary; partial evenings and rotation are welcome. Please keep time for family, fellowship and rest.
Progress so far
Updated October 24: sound-insulation panels were installed October 23 with the right cutting tool. Both ceilings are installed; wall drywall, joint and surface finishing and paint remain.
Milestones reached
- Room framing assembledThe basic wood frames are in place.
- Stained boards preparedVolunteers prepared the stained/painted boards; exterior installation is now complete.
- Further connections reinforcedAdditional brackets and stronger wall connections were added in Week 2.
- Wall reinforcement completeFinal reinforcement to the wall is complete.
- Exterior stained boards installedInstallation of the stained exterior-facing boards is complete.
- Both rooms’ ceiling drywall installedFirst room installed October 20; the more difficult second room finished October 21. Drywall joint and surface finishing remain.
- Light switches loweredOctober 21: Alexander addressed George’s suggestion by lowering the light switches for accessibility.
- Sound-insulation panels installedOctober 23: with the right cutting tool, Ron, Adam, Ken Fong (嘉辉), Phoenix (小毛) and Phoenix’s dad installed the panels.
Next · Week 4 planning
- Wall drywall and remaining workDaily priorities and work sequence to confirm with Ron; no completion date is promised.
- Thursday cleanup · Friday restCleanup needed October 29; helpers and time to confirm. No construction or cleanup shift October 30.
Still ahead
- Glass windows and doorsInstall the room windows and doors.
- New door openings to the foyerCreate the planned new doorway exits to the foyer.
- Drywall and paintBoth ceilings and the sound-insulation panels are installed. Wall drywall, joint and surface finishing and paint remain; Ron confirms the next sequence.
- Lighting and switchesLight switches have been lowered to address accessibility height requirements; the remaining lighting and switch work still needs completion.
- VentilationInstall ventilation; coordinate power, airflow and the duct route.
- TV and small speakersMount the TV and small speakers for parents and small-group use.
- AV network and wiringComplete the AV/network connections and wiring.
Before closing the walls: Confirm the remaining electrical, AV/network and ventilation routes with the relevant skilled helpers. Sound-insulation panels are installed; Ron confirms the next drywall sequence. This is the remaining project scope, not a promise to finish everything in Week 4.
Choose a date. Choose a role.
Contact Thian-Peng (添平) with the date, role and times you can help, plus tool experience or lifting restrictions. Construction and practical support are separate. A signup is confirmed only when it appears in the roster.
You do not need to be a professional builder, own tools, or have been involved in the design. Tell us your experience so suitable work can be assigned.
Glass, electrical, ventilation and structural work need suitable skilled helpers. Open volunteer slots do not authorize specialist tasks. Ron confirms safe assignments; building access is arranged separately.
About 2–3 support people as needed; tasks may be combined. Light-duty support is welcome, with no heavy lifting.
No weekend shift is added here. Any weekend work needs separate confirmation around church activities.
Before each work session
- Confirm that date’s attendance, start/finish times and opening/locking arrangements.
- Ron confirms suitable tasks, tools and the day’s sequence. Coordinate specialist work before closing walls.
- Arrange food and practical support only after confirmation. Light-duty helpers must not lift heavy items.
- Keep floor protection in place unless a change is agreed. Confirm Thursday, October 29 cleanup helpers and timing; Friday, October 30 is off for rest.
Youth Scripture-writing Opportunity
Ron agreed in principle to Scripture being written with markers on approved interior framing before it is covered, with photos as a record. Timing and surfaces must be coordinated with Ron. Young people must be supervised in a safe area separate from hazardous work; no activity time is booked yet.
Background
For what the rooms are, why we are building them, and what the congregation asked for, see Sanctuary Rooms: What We're Building and What We Need From You.
招募弟兄姊妹参与主堂房间施工
第四周 · 2026 年 10 月 26–30 日
同心建造,一步一步往前。
10 月 23 日(周五)有了合适的切割工具,隔音板已安装。荣强弟兄带领 Adam、Ken(嘉辉)、Phoenix(小毛)和她的爸爸一起完成安装。Peggy 和 Ally 协助清洁,简牧师为团队预备了温暖的家常饭菜。
状态:第四周:Roy 已确认 10 月 28、29 日(周三、周四)担任施工帮手,Qiang Li(李强)也已确认 10 月 29 日(周四)参与施工。合适分工由荣强安排。这两天每天还需要周三还需要 2 位施工帮手;位施工帮手,周四还需要 1 位;周一及周二每天仍有 3 个空缺。每天工作、时间、其他帮手及餐食人员仍待确认。10 月 29 日(周四)需要清洁,人员及时间待确认;10 月 30 日(周五)休息,不安排施工或清洁。
最后更新:2026 年 10 月 24 日。
第四周 · 帮手报名岗位
Roy 已确认 10 月 28、29 日(周三、周四)参与施工,Qiang Li(李强)也已确认 10 月 29 日(周四)参与施工。其他帮手、餐食人员和时间仍待确认。10 月 29 日(周四)清洁,10 月 30 日(周五)休息,最新安排请查看排班。
第四周先列待确认安排:沿用除荣强以外 3 位施工帮手的目标,另按需要安排约 2–3 位实际支援人员。每天工作、时间和其余人员出席仍待确认,不自动沿用上周名单。
即使当晚人手已齐,愿意参与仍然欢迎。每天参与都是自愿的,可参与部分时段,也可轮替;请顾及家庭、团契及休息。
建设进度一览
10 月 24 日更新:10 月 23 日有了合适工具,隔音板已安装。两间天花板已安装;墙面石膏板、接缝及表面处理和油漆仍待完成。
已达到的里程碑
- 房间木框架已搭起基本木框架已就位。
- 外侧木板已刷好弟兄姊妹已预备好木板;外侧木板安装现已完成。
- 已增设连接加固第二周已加装连接件,加强部分结构与墙面的连接。
- 墙面最后加固已完成与墙面的最后加固已完成。
- 外侧木板安装已完成已刷好外侧木板的安装已完成。
- 两间房间天花板石膏板均已安装10 月 20 日安装第一间;10 月 21 日完成较困难的另一间。石膏板接缝及表面处理仍未完成。
- 灯光开关已调低10 月 21 日:Alexander 回应 George(耀基)的建议,按无障碍要求调低灯光开关。
- 隔音板已安装10 月 23 日:有了合适的切割工具,荣强弟兄、Adam、Ken(嘉辉)、Phoenix(小毛)和她的爸爸一起完成安装。
下一步 · 第四周安排
- 墙面石膏板及其余工作每天工作重点及工序由荣强确认,尚未承诺完工日期。
- 周四清洁 · 周五休息10 月 29 日需要清洁,人员及时间待确认;10 月 30 日不安排施工或清洁。
接下来要完成
- 玻璃窗及门安装房间玻璃窗和门。
- 通往门厅的新门洞开出计划中通往门厅的新门口。
- 石膏板及油漆两间天花板及隔音板已安装。墙面石膏板、接缝及表面处理和油漆仍待完成;下步工序由荣强确认。
- 灯具及开关灯光开关已按无障碍高度要求调低;其余灯具及开关工作仍待完成。
- 通风设备安装通风设备,协调电源、气流及风管路线。
- 电视及小音箱为家长及小组使用,安装电视和小音箱。
- 影音网络及布线完成影音、网络连接及相关布线。
封墙前先协调:与相关有经验的帮手确认剩余电线、影音网络及通风路线。隔音板已安装,下步石膏板工序由荣强确认。以上是项目尚余工作,不代表承诺在第四周全部完成。
不需要是专业建造人员,也不需要自备工具或曾参与设计。请说明自己的经验,方便安排合适的工作。
玻璃、电工、通风及结构工作需要合适且有经验的帮手。报名一般施工岗位,不等于可以承担这些工作。由荣强确认安全分工,开门安排另行确认。
按需要合计约 2–3 位,岗位可兼任。欢迎轻量支援,不搬重物。
此处不新增周末施工;如需做工,须另行确认并协调教会活动。
每次开工前
- 逐日确认出席、开始及结束时间,以及开门锁门安排。
- 由荣强确认合适的工作、工具及当天工序;封墙前协调相关专门工作。
- 确认后才安排餐食及实际支援;轻量支援人员不搬重物。
- 地板保护继续保留,除非另有商定;确认 10 月 29 日(周四)清洁人员及时间,10 月 30 日(周五)休息。
年轻人写经文的机会
荣强原则上同意在内侧框架封板前,用记号笔在获准的位置写经文,并拍照留念。时间和位置须与荣强协调。年轻人须有人带领,在与危险施工分开的安全区域进行;活动时间尚未安排。
背景资料
关于这两间房间是什么、为什么要建、以及会众提出了哪些需要,请参阅主堂房间:我们要建什么,需要你回应什么。
招募弟兄姊妹參與主堂房間施工
第四周 · 2026 年 10 月 26–30 日
同心建造,一步一步往前。
10 月 23 日(週五)有了合適的切割工具,隔音板已安裝。榮強弟兄帶領 Adam、Ken(嘉輝)、Phoenix(小毛)和她的爸爸一起完成安裝。Peggy 和 Ally 協助清潔,簡牧師為團隊預備了温暖的家常飯菜。
狀態:第四周:Roy 已確認 10 月 28、29 日(週三、週四)擔任施工幫手,Qiang Li(李強)也已確認 10 月 29 日(週四)參與施工。合適分工由榮強安排。這兩天每天還需要週三還需要 2 位施工幫手;位施工幫手,週四還需要 1 位;週一及週二每天仍有 3 個空缺。每天工作、時間、其他幫手及餐食人員仍待確認。10 月 29 日(週四)需要清潔,人員及時間待確認;10 月 30 日(週五)休息,不安排施工或清潔。
最後更新:2026 年 10 月 24 日。
第四周 · 幫手報名崗位
Roy 已確認 10 月 28、29 日(週三、週四)參與施工,Qiang Li(李強)也已確認 10 月 29 日(週四)參與施工。其他幫手、餐食人員和時間仍待確認。10 月 29 日(週四)清潔,10 月 30 日(週五)休息,最新安排請查看排班。
第四周先列待確認安排:沿用除榮強以外 3 位施工幫手的目標,另按需要安排約 2–3 位實際支援人員。每天工作、時間和其餘人員出席仍待確認,不自動沿用上週名單。
即使當晚人手已齊,願意參與仍然歡迎。每天參與都是自願的,可參與部分時段,也可輪替;請顧及家庭、團契及休息。
建設進度一覽
10 月 24 日更新:10 月 23 日有了合適工具,隔音板已安裝。兩間天花板已安裝;牆面石膏板、接縫及表面處理和油漆仍待完成。
已達到的里程碑
- 房間木框架已搭起基本木框架已就位。
- 外側木板已刷好弟兄姊妹已預備好木板;外側木板安裝現已完成。
- 已增設連接加固第二週已加裝連接件,加強部分結構與牆面的連接。
- 牆面最後加固已完成與牆面的最後加固已完成。
- 外側木板安裝已完成已刷好外側木板的安裝已完成。
- 兩間房間天花板石膏板均已安裝10 月 20 日安裝第一間;10 月 21 日完成較困難的另一間。石膏板接縫及表面處理仍未完成。
- 燈光開關已調低10 月 21 日:Alexander 回應 George(耀基)的建議,按無障礙要求調低燈光開關。
- 隔音板已安裝10 月 23 日:有了合適的切割工具,榮強弟兄、Adam、Ken(嘉輝)、Phoenix(小毛)和她的爸爸一起完成安裝。
下一步 · 第四周安排
- 牆面石膏板及其餘工作每天工作重點及工序由榮強確認,尚未承諾完工日期。
- 週四清潔 · 週五休息10 月 29 日需要清潔,人員及時間待確認;10 月 30 日不安排施工或清潔。
接下來要完成
- 玻璃窗及門安裝房間玻璃窗和門。
- 通往門廳的新門洞開出計劃中通往門廳的新門口。
- 石膏板及油漆兩間天花板及隔音板已安裝。牆面石膏板、接縫及表面處理和油漆仍待完成;下步工序由榮強確認。
- 燈具及開關燈光開關已按無障礙高度要求調低;其餘燈具及開關工作仍待完成。
- 通風設備安裝通風設備,協調電源、氣流及風管路線。
- 電視及小音箱為家長及小組使用,安裝電視和小音箱。
- 影音網絡及佈線完成影音、網絡連接及相關佈線。
封牆前先協調:與相關有經驗的幫手確認剩餘電線、影音網絡及通風路線。隔音板已安裝,下步石膏板工序由榮強確認。以上是項目尚餘工作,不代表承諾在第四周全部完成。
不需要是專業建造人員,也不需要自備工具或曾參與設計。請説明自己的經驗,方便安排合適的工作。
玻璃、電工、通風及結構工作需要合適且有經驗的幫手。報名一般施工崗位,不等於可以承擔這些工作。由榮強確認安全分工,開門安排另行確認。
按需要合計約 2–3 位,崗位可兼任。歡迎輕量支援,不搬重物。
此處不新增週末施工;如需做工,須另行確認並協調教會活動。
每次開工前
- 逐日確認出席、開始及結束時間,以及開門鎖門安排。
- 由榮強確認合適的工作、工具及當天工序;封牆前協調相關專門工作。
- 確認後才安排餐食及實際支援;輕量支援人員不搬重物。
- 地板保護繼續保留,除非另有商定;確認 10 月 29 日(週四)清潔人員及時間,10 月 30 日(週五)休息。
年輕人寫經文的機會
榮強原則上同意在內側框架封板前,用記號筆在獲准的位置寫經文,並拍照留念。時間和位置須與榮強協調。年輕人須有人帶領,在與危險施工分開的安全區域進行;活動時間尚未安排。
背景資料
關於這兩間房間是什麼、為什麼要建、以及會眾提出了哪些需要,請參閱主堂房間:我們要建什麼,需要你回應什麼。