2026-10 Sanctuary Rooms Installation Schedule 主堂房间安装排班

Status: Planning, not a confirmed daily roster. Last updated: September 24, 2026. Times are local to Saskatoon.

The glass has arrived. Ron Xie (谢荣强) will lead the installation. The proposed work window is October 5–9, 5:30–9:30 pm each evening. Please confirm the actual dates and each person's availability before treating a row as staffed.

People and responsibilities

  • Installation lead: Ron. He directs the work and decides what can be done safely each night.
  • Helpers who have offered to help: 杜加坤 (Du Jia Kun) and Gordon. Their availability for October 5–9 has not yet been assigned to specific evenings.
  • On-site coordinator/support: To be named. Handle building access, keep the work area clear, and facilitate the work. Ron directs the installation.
  • Daily crew target: Ron needs 2–3 handy helpers each evening. The coordinator should confirm the count with Ron and fill the roster below.

Schedule and crew

Date and timePlanConfirmed helpersOn-site support
Sun, Oct 4
2:00 pm
Plan:Ron to buy supplies; loading and unloading help needed.Confirmed helpers:To confirmOn-site support:To confirm
Mon, Oct 5
5:30–9:30 pm
Plan:Installation work, tasks set by Ron.Confirmed helpers:To confirmOn-site support:To confirm
Tue, Oct 6
5:30–9:30 pm
Plan:Installation work, tasks set by Ron.Confirmed helpers:To confirmOn-site support:To confirm
Wed, Oct 7
5:30–9:30 pm
Plan:Installation work, tasks set by Ron.Confirmed helpers:To confirmOn-site support:To confirm
Thu, Oct 8
5:30–9:30 pm
Plan:Installation work, tasks set by Ron.Confirmed helpers:To confirmOn-site support:To confirm
Fri, Oct 9
5:30–9:30 pm
Plan:Installation work, tasks set by Ron.Confirmed helpers:To confirmOn-site support:To confirm

Contingency: Part of Saturday, October 10, only if needed and coordinated around church activities. If more time is needed, work may continue the following week. Neither is a confirmed shift.

Before work starts

  1. Ron confirms the nightly tasks, helper count, and any glass-handling or other safety needs.
  2. Confirm each helper's actual evenings and fill the roster. An offer to help is not a daily commitment.
  3. Name the on-site coordinator/support and confirm who opens and locks the building.
  4. Arrange Sunday loading, weekday supply runs, and optional refreshments or photos.

Background: Sanctuary Rooms Build Team.

状态:计划中,每天的帮手名单尚未确认。最后更新:2026 年 9 月 24 日。时间均为萨斯卡通当地时间。

玻璃已经到了。安装工作由谢荣强带领。计划于 10 月 5 日至 9 日每晚 5:30–9:30 施工。实际日期和每人的出席时间仍须确认,不能把下面的空位当作已有人负责。

人员与分工

  • 安装负责人:荣强。他指挥施工,并决定每晚哪些工作可以安全进行。
  • 已表示愿意帮忙:杜加坤和 Gordon。两人在 10 月 5 日至 9 日各晚的出席安排尚未确认。
  • 现场协调/支援同工:待定。负责开门、保持施工区域畅通,并协助现场工作顺利进行。安装工作由荣强指挥。
  • 每晚人数:荣强每晚需要 2–3 位会动手做工的帮手。协调同工需向荣强确认人数,并填写以下名单。

施工时间及每日名单

日期及时间安排已确认帮手现场支援
10 月 4 日(主日)
下午 2:00
安排:荣强采购材料,需要帮忙搬运和装卸。已确认帮手:待确认现场支援:待确认
10 月 5 日(周一)
晚上 5:30–9:30
安排:安装施工;具体工作由荣强安排。已确认帮手:待确认现场支援:待确认
10 月 6 日(周二)
晚上 5:30–9:30
安排:安装施工;具体工作由荣强安排。已确认帮手:待确认现场支援:待确认
10 月 7 日(周三)
晚上 5:30–9:30
安排:安装施工;具体工作由荣强安排。已确认帮手:待确认现场支援:待确认
10 月 8 日(周四)
晚上 5:30–9:30
安排:安装施工;具体工作由荣强安排。已确认帮手:待确认现场支援:待确认
10 月 9 日(周五)
晚上 5:30–9:30
安排:安装施工;具体工作由荣强安排。已确认帮手:待确认现场支援:待确认

备用安排:如有需要,10 月 10 日(周六)可避开教会活动,安排部分时间收尾;若仍未完成,可延续到下一周。这些日期目前都不是已确认的班次。

开工前要确认

  1. 请荣强确认每天的工作、所需帮手人数,以及搬运玻璃等工作的安全要求。
  2. 逐一确认帮手哪几晚能来,再填写名单。愿意帮忙不等于每晚都能出席。
  3. 确定现场协调/支援同工,并确认谁负责开门和锁门。
  4. 安排主日搬运、平日补购材料,以及可提供的茶点或拍照支援。

背景:主堂房间建堂招募。