Schedule
Status: Planned dates; weekday helper assignments confirmed. Frank is confirmed for Sunday; one more person is needed for loading/unloading, and some weekday support roles remain open.
Last updated: September 24, 2026.
The glass has arrived. Ron Xie (谢荣强) will lead the installation. The proposed work window is October 5–9, 5:30–9:30 pm each evening. Du Jia Kun and Gordon are confirmed to help each evening from Monday through Friday. The goal is four helpers each evening, in addition to Ron. Two more are needed to reach that goal; additional helpers are welcome so Gordon and 杜加坤 can rotate and take breaks. Ron directs the work.
People and responsibilities
- Installation lead: Ron. He directs the work and decides what can be done safely each night.
- Confirmed weekday helpers: 杜加坤 (Du Jia Kun) and Gordon, Monday through Friday, October 5–9.
- On-site coordinator/support: Pastor Philip on Monday, October 5; Tuesday–Friday support remains to be named. Handle building access, keep the work area clear, and facilitate the work. Ron directs the installation. Lily is bringing refreshments and taking photos on Monday.
- Daily crew target: Four handy helpers each evening, in addition to Ron. 杜加坤 and Gordon are confirmed, so two more are needed for each weekday shift. More than four are welcome so the crew can take breaks.
Schedule and crew
Support areas: Materials / loading Build crew / relief On-site Refreshments / photos
| Date and time | Plan | Confirmed helpers | Other support | Still needed |
|---|---|---|---|---|
| Sun, Oct 4 2:00 pm | Plan:Ron purchases supplies; Frank is confirmed to help. | Confirmed helpers:Frank | Other support: — | Still needed: One more person for loading and unloading |
| Mon, Oct 5 5:30–9:30 pm | Plan:Installation work, tasks set by Ron. | Confirmed helpers:杜加坤 (Du Jia Kun), Gordon | Other support: Pastor Philip · on-site support Lily · refreshments and photos | Still needed: 2 more to reach 4 helpers; more helpers welcome for breaks |
| Tue, Oct 6 5:30–9:30 pm | Plan:Installation work, tasks set by Ron. | Confirmed helpers:杜加坤 (Du Jia Kun), Gordon | Other support: To confirm | Still needed: 2 more to reach 4 helpers; more helpers welcome for breaks On-site support |
| Wed, Oct 7 5:30–9:30 pm | Plan:Installation work, tasks set by Ron. | Confirmed helpers:杜加坤 (Du Jia Kun), Gordon | Other support: To confirm | Still needed: 2 more to reach 4 helpers; more helpers welcome for breaks On-site support |
| Thu, Oct 8 5:30–9:30 pm | Plan:Installation work, tasks set by Ron. | Confirmed helpers:杜加坤 (Du Jia Kun), Gordon | Other support: To confirm | Still needed: 2 more to reach 4 helpers; more helpers welcome for breaks On-site support |
| Fri, Oct 9 5:30–9:30 pm | Plan:Installation work, tasks set by Ron. | Confirmed helpers:杜加坤 (Du Jia Kun), Gordon | Other support: To confirm | Still needed: 2 more to reach 4 helpers; more helpers welcome for breaks On-site support |
Contingency: Part of Saturday, October 10, only if needed and coordinated around church activities. If more time is needed, work may continue the following week. Neither is a confirmed shift.
Before work starts
- Ron confirms the nightly tasks, helper count, and any glass-handling or other safety needs.
- 杜加坤 and Gordon are confirmed Monday–Friday. Find two more weekday helpers for the four-person target; more helpers welcome for breaks. Frank is confirmed for Sunday; find one more person for loading/unloading.
- Confirm Tuesday–Friday on-site support and who opens and locks the building each day.
- Find one more Sunday loading/unloading helper and arrange any weekday supply runs. Lily covers Monday refreshments and photos.
Background: Sanctuary Rooms Build Team.
状态:日期计划中,周一至周五的施工帮手已确认。Frank 已确认主日参与;装卸还需 1 位帮手,平日部分现场支援也待安排。
最后更新:2026 年 9 月 24 日。
玻璃已经到了。安装工作由谢荣强带领。计划于 10 月 5 日至 9 日每晚 5:30–9:30 施工。杜加坤和 Gordon 已确认周一至周五每晚帮忙。目标是除荣强以外,每晚有 4 位施工帮手。目前还差 2 位;超过 4 位也欢迎,大家可以轮替,让杜加坤和 Gordon 有时间休息。具体工作由荣强安排。
人员与分工
- 安装负责人:荣强。他指挥施工,并决定每晚哪些工作可以安全进行。
- 已确认的平日帮手:杜加坤和 Gordon,10 月 5 日至 9 日(周一至周五)每晚参与。
- 现场协调/支援同工:10 月 5 日(周一)由 Pastor Philip 负责;周二至周五待定。负责开门、保持施工区域畅通,并协助现场工作顺利进行。安装工作由荣强指挥。周一茶点和拍照由 Lily 负责。
- 每晚人数:除荣强以外,目标是每晚 4 位会动手做工的帮手。杜加坤和 Gordon 已确认,周一至周五每天还需 2 位。更多帮手也欢迎,方便大家轮替休息。
施工时间及每日名单
支援类别:采购/装卸 施工帮手/轮替 现场支援 茶点/拍照
| 日期及时间 | 安排 | 已确认帮手 | 其他支援 | 还需要 |
|---|---|---|---|---|
| 10 月 4 日(主日) 下午 2:00 | 安排:荣强采购材料;Frank 已确认协助。 | 已确认帮手:Frank | 其他支援:— | 还需要:再找 1 位帮忙装卸材料 |
| 10 月 5 日(周一) 晚上 5:30–9:30 | 安排:安装施工;具体工作由荣强安排。 | 已确认帮手:杜加坤、Gordon | 其他支援:Pastor Philip · 现场支援 Lily · 茶点、拍照 | 还需要:再找 2 位达到每晚 4 位;更多帮手可轮替休息 |
| 10 月 6 日(周二) 晚上 5:30–9:30 | 安排:安装施工;具体工作由荣强安排。 | 已确认帮手:杜加坤、Gordon | 其他支援:待确认 | 还需要:再找 2 位达到每晚 4 位;更多帮手可轮替休息 现场支援同工 |
| 10 月 7 日(周三) 晚上 5:30–9:30 | 安排:安装施工;具体工作由荣强安排。 | 已确认帮手:杜加坤、Gordon | 其他支援:待确认 | 还需要:再找 2 位达到每晚 4 位;更多帮手可轮替休息 现场支援同工 |
| 10 月 8 日(周四) 晚上 5:30–9:30 | 安排:安装施工;具体工作由荣强安排。 | 已确认帮手:杜加坤、Gordon | 其他支援:待确认 | 还需要:再找 2 位达到每晚 4 位;更多帮手可轮替休息 现场支援同工 |
| 10 月 9 日(周五) 晚上 5:30–9:30 | 安排:安装施工;具体工作由荣强安排。 | 已确认帮手:杜加坤、Gordon | 其他支援:待确认 | 还需要:再找 2 位达到每晚 4 位;更多帮手可轮替休息 现场支援同工 |
备用安排:如有需要,10 月 10 日(周六)可避开教会活动,安排部分时间收尾;若仍未完成,可延续到下一周。这些日期目前都不是已确认的班次。
开工前要确认
- 请荣强确认每天的工作、所需帮手人数,以及搬运玻璃等工作的安全要求。
- 杜加坤和 Gordon 已确认周一至周五每晚参与。周一至周五每天再找 2 位施工帮手达到 4 位目标;更多帮手可轮替休息。Frank 已确认主日参与;再找 1 位装卸帮手。
- 确定周二至周五的现场支援同工,并确认每天谁负责开门和锁门。
- 再找 1 位主日装卸帮手,并安排平日补购材料。周一茶点和拍照由 Lily 负责。
背景:主堂房间建堂招募。