Schedule
WEEK 3 · OCTOBER 19–23, 2026
Building together, one step at a time.
Wall reinforcementreinforcement, exterior stained boards and exteriorceiling stained-boarddrywall installationin both rooms are complete. CeilingThe drywallmore difficult second ceiling was installed in one room on Tuesday, October 20; the crew will continue ceiling drywall work onfinished Wednesday, October 21,21. ledThursday, byOctober 22: install sound insulation and wall drywall under Brother Ron.Ron’s direction.
Status: Wall reinforcement and exterior stained-board installation are complete; Brother Du (杜加坤) is confirmed for cutting on Thursday, October 22. 邓集 is confirmed to assist in installation on October 19, 21 and 22, 5:30–9:00 pm each day. Ken Fong (嘉辉) is confirmed as a build helper on Monday, Tuesday, Wednesday and Friday, October 19, 20, 21 and 23; Ron confirms his task assignments. Adam is confirmed as a build helper Tuesday–Friday, October 20–23; Ron confirms his task assignments. Monday through Thursday’s helper headcounts are covered. George (耀基) is also confirmed as a build helper on Tuesday, October 20, to help with the remaining work; Ron confirms task assignments. Gabriel assisted with installation on Tuesday, October 20, and is confirmed to assist again on Wednesday, October 21. Construction openings: Friday 1. Support slots are open separately.
Last updated: October 20,21, 2026.
Keep the purpose in view
As we build, our hope is to help young families stay connected to worship, reduce stair trips for parents and grandparents caring for children, and share the space across ministries. We are putting welcome and care into practice, across generations.

Progress so far
Milestones updated October 20.21. WallBoth reinforcementrooms andnow exterior stained boards are complete;have ceiling drywall installed. Thursday’s next work continuesis Wednesday.sound insulation and wall drywall; joints, surface finishing and paint remain.
Milestones reached
- Room framing assembledThe basic wood frames are in place.
- Stained boards preparedVolunteers prepared the stained/painted boards; exterior installation is now complete.
- Further connections reinforcedAdditional brackets and stronger wall connections were added in Week 2.
- Wall reinforcement completeFinal reinforcement to the wall is complete.
- Exterior stained boards installedInstallation of the stained exterior-facing boards is complete.
OneBothroom’srooms’ ceiling drywall installedCeiling drywall installed in oneFirst roomon Tuesday,installed October 20;thisthedoesmorenotdifficultmeansecondallroomdrywallfinished October 21. Drywall joint and surface finishingisremain.- Light
complete.switches loweredOctober 21: Alexander addressed George’s suggestion by lowering the light switches for accessibility.
UnderwayNext · WednesdayThursday focus
ContinueInstallceilingsound insulationPlanned Thursday, October 22, before wall drywall closes the framing.- Install wall drywall
Wednesday,Planned Thursday, October21:22,continueafterceilingsounddrywallinsulation;workRonunderconfirmsBrothertheRon’s direction.sequence.
Still ahead
- Glass windows and doorsInstall the room windows and doors.
- New door openings to the foyerCreate the planned new doorway exits to the foyer.
Sound insulationInstall sound insulation before closing the walls.- Drywall and paint
CompleteBoththeceilingsremainingare installed. Wall drywallinstallation,is planned for Thursday, followed by remaining joint and surfacefinishing,finishingthenand paint.One room’s ceiling drywall was installed October 20. - Lighting and switches
CompleteLight switches have been lowered to address accessibility height requirements; the remaining lighting and switchinstallation.work still needs completion. - VentilationInstall ventilation; coordinate power, airflow and the duct route.
- TV and small speakersMount the TV and small speakers for parents and small-group use.
- AV network and wiringComplete the AV/network connections and wiring.
Before closing the walls: Coordinate electrical, AV/network and ventilation routes, then insulation and drywall. Ron confirms the work sequence with the relevant skilled helpers. This is the remaining project scope, not a promise to finish everything in Week 3.
Week 3 · helper slots
Continue the focused-role model: three construction helpers besides Ron, plus about two or three practical-support people as needed. Ron assigns suitable tasks as the work changes. George fills one of Monday’s construction-helper slots.
Everyone is welcome to take part, even when a shift is covered. Every workday is voluntary; partial evenings and rotation are welcome. Please keep time for family, fellowship and rest.
| Date and time | Work focus | Confirmed build helpers | Practical support | Open build slots |
|---|---|---|---|---|
| Mon, Oct 19Times to confirm | Work focus: George focuses on final wall reinforcement. Brother Ron leads the crew installing the remaining stained exterior-facing boards. | Confirmed helpers: George (耀基) Final wall reinforcement邓集 Assist in installation 5:30–9:00 pmKen Fong (嘉辉) Build helper · tasks assigned by Ron | Support: Materials / site organization Pastor PhilipFood preparation Dennis & Amy Lily 师母 | Open build slots: CoveredRon confirms task assignments, including cutting / preparation. |
| Tue, Oct 20Times to confirm | Work focus: Wall reinforcement and exterior stained-board installation completed. Ceiling drywall installed in one room. | Confirmed helpers: Adam Build helper · tasks assigned by RonGeorge (耀基) Build helper · tasks assigned by RonKen Fong (嘉辉) Build helper · tasks assigned by RonGabriel Assist in installation · attended | Support: Materials / site organization OpenFood preparation Vincent & Monica Plan to prepare roasted beef, pork chops and chicken.Snack preparation Ha Jie (霞姐) · A snack | Open build slots: CoveredTasks include cutting / preparation and installation; Ron confirms the assignments. |
| Wed, Oct 21Times to confirm | Work focus: | Confirmed helpers: 邓集 Assist in installation 5:30–9:00 pmAdam Build helper · tasks assigned by RonKen Fong (嘉辉) Build helper · tasks assigned by RonGabriel Assist in installation | Support: Heated food; prepared fruit, salad and longan tea.Electrical adjustment Alexander Lowered the light switches following George’s suggestion to address accessibility height requirements.Dinner Leftovers from Tuesday, October 20. | Open build slots: CoveredTasks include cutting / preparation and installation; Ron confirms the assignments. |
| Thu, Oct 22Times to confirm | Work focus: | Confirmed helpers: Brother Du (杜加坤) Cutting / preparation邓集 Assist in installation 5:30–9:00 pmAdam Build helper · tasks assigned by Ron | Support: Materials / site organization OpenFood preparation Catherine (牛慧) | Open build slots: CoveredRon confirms task assignments. |
| Fri, Oct 23Times to confirm | Work focus: Continue the next ready tasks from the work list. Ron confirms the daily sequence; specialist work is coordinated separately. | Confirmed helpers: Adam Build helper · tasks assigned by RonKen Fong (嘉辉) Build helper · tasks assigned by Ron | Support: Materials / site organization OpenCleanup Peggy Ter Family (戴家) CoveredMeal preparation Pastor Kaan | Open build slots: 1 more build helperBuild helpers · 1 openTasks include cutting / preparation and installation; Ron confirms the assignments. |
About 2–3 support people as needed; tasks may be combined. Cleanup helpers are needed on Friday only. Light-duty support is welcome, with no heavy lifting.
Choose a date. Choose a role.
Contact Thian-Peng (添平) with the date, role and times you can help, plus tool experience or lifting restrictions. Construction and practical support are separate. A signup is confirmed only when it appears in the roster.
Glass, electrical, ventilation and structural work need suitable skilled helpers. Open volunteer slots do not authorize specialist tasks. Ron confirms safe assignments; building access is arranged separately.
No weekend shift is added here. Any weekend work needs separate confirmation around church activities.
Before each work session
- Confirm that date’s attendance, start/finish times and opening/locking arrangements.
- Ron confirms suitable tasks, tools and the day’s sequence. Coordinate specialist work before closing walls.
- Arrange food and practical support only after confirmation. Light-duty helpers must not lift heavy items.
- Keep floor protection in place unless a change is agreed. Confirm cleanup timing around church activities.
Previous weeks
Earlier schedules and participation records are kept below. Historical staffing gaps are not current recruitment needs.
Week 2 · October 13–16
Historical plan and role confirmations, including Friday’s reported actual participation. This is not the Week 3 signup list.
Status: Week 2: Tuesday, Wednesday and Thursday construction roles are covered. Friday’s actual construction and support participants are recorded below. Susan (晓英) provides Wednesday on-site support; Catherine (牛慧) delivers food and provides Thursday on-site support. Friday’s cleanup is complete for Saturday’s activities.
Last updated: October 17, 2026.
Week 2 is planned for Tuesday–Friday, October 13–16, led by Ron Xie (谢荣强). Tuesday starts at 5:30 pm; its finish time and the remaining evenings’ times are to be confirmed. The focused roles are covered by three build helpers alongside Ron, plus about two or three people for practical support as needed. Everyone is welcome to take part, even when a shift is covered; tasks will be assigned by Ron. Participation is voluntary on every workday, and helpers can rotate rather than attend every evening.
Week 2 schedule and crew
| Date and time | Plan | Assigned construction roles | Support roles | Open construction roles |
|---|---|---|---|---|
| Tue, Oct 13 5:30 pm start; finish to confirm | Plan: Strengthen framing/connections, then install the stained exterior-facing boards. Door work as directed by Ron. | Assigned roles: Cutting + pre-drilling: Adam and Gabriel Ron assigns the split. Installation: Ken Fong (嘉辉) | Other support: Judy · on-site support Janet · on-site support Judy · bringing a dish Ha Jie (霞姐) · bringing a dish | Open construction roles: Covered |
| Wed, Oct 14 Evening; time to confirm | Plan: Strengthen framing/connections, then install the stained exterior-facing boards. Door work as directed by Ron. | Assigned roles: Cutting + pre-drilling: Adam and Gabriel Pre-drilling or installation: 邓集 Ron assigns the three helpers across cutting, pre-drilling and installation. | Support roles: Susan (晓英) · on-site support: moving materials and cleaning; arrival time to confirm Additional practical support welcome as needed; about 2–3 support people in total. | Open construction roles: Covered |
| Thu, Oct 15 — daytime 10:00 am access | Plan: Sean comes for wiring. This daytime visit is separate from the evening construction shift. | Assigned roles: Sean · wiring | Support roles: Ericson · arrives at 10:00 am to give Sean access to the church | Open construction roles: Not applicable — daytime wiring/access visit |
| Thu, Oct 15 Evening; time to confirm | Plan: Strengthen framing/connections, then install the stained exterior-facing boards. Door work as directed by Ron. | Assigned roles: Cutting: Du Jiakun Pre-drilling or installation: 邓集 Installation: Enoch Zheng (郑以诺) Ron assigns suitable tasks and the final split. | Support roles: Catherine (牛慧) · food delivery Catherine (牛慧) · on-site support Materials / on-site organization · Open as needed Cleanup · Open as needed About 2–3 support people in total, as needed; tasks can be combined. Arrival times to confirm. | Open construction roles: Covered |
| Fri, Oct 16 Actual participation | Work completed: Continued reinforcement and installation of the stained exterior-facing boards. George and Adam worked on brackets and stronger wall connections while Ron led the board installation. The team cleaned up for Saturday’s Cantonese worship and 5L2F. | Attended: Work lead: Ron Xie (谢荣强) Reinforcement: George (耀基) and Adam Other build helpers: Jacob (曲华) Sarah (小滨) Luke Ken Fong (嘉辉) | Support provided: Ericson · helped repair the security system Peggy · site cleaning Thian-Peng (添平) and Ally · swept and collected leaves at the front entrance Pastor Kaan · came in the early afternoon and cooked the crew’s meal Yi Kiu (二娇) · brought a tart Everyone helped with the final cleanup for Saturday’s Cantonese worship and 5L2F. | Construction coverage: Covered |
Sign up for an open role: Contact Thian-Peng with the date, role, and times you can help (for example, “Thursday — pre-drilling”). Let us know your tool experience or any lifting restrictions. Ron confirms suitable assignments and provides guidance. Construction and support are separate; a support volunteer may combine tasks. The roster is updated after attendance is confirmed.
Week 2: roles and expectations
- Ron — work lead: Ron measures, makes decisions, directs the sequence and safety, and carries out fastening where his experience keeps the work moving. Helpers follow his measurements and instructions; not every task is repetitive.
- Cutting — 1 helper: Cut boards to Ron’s measurements. Ron assigns a suitable helper and provides guidance; cutters may rotate.
- Pre-drilling — 1 helper: Prepare the holes Ron identifies so the next installation step can proceed.
- Fastening / installation — 1 helper: Assist Ron with fastening and installation as directed. Roles may flex with the task.
- Practical support — about 2–3 people, as needed: Move suitable materials, keep things organized, clean up, and encourage the team. Support is separate from the three construction positions. Light-duty volunteers, including Jacqueline and Sinnie if they join, must not lift heavy items.
- Confirmed for Tuesday, October 13: Adam and Gabriel help with cutting and pre-drilling; Ron assigns the split. Ken Fong (嘉辉) assists Ron with installation. Judy and Janet provide on-site support; Judy and Ha Jie (霞姐) each bring a dish.
- Confirmed for Wednesday, October 14: Adam and Gabriel join for cutting/pre-drilling, alongside 邓集 for pre-drilling or installation. The three-helper crew is covered; Ron assigns the final split across the construction roles. Susan (晓英) provides on-site support with moving materials and cleaning. Her arrival time is to be confirmed.
- Thursday daytime access, October 15: Ericson arrives at 10:00 am to give Sean access for wiring. This is separate from the evening construction shift.
- Confirmed for Thursday, October 15: Du Jiakun handles cutting; 邓集 helps with pre-drilling or installation; Enoch Zheng (郑以诺) assists with installation. The three construction-helper roles are covered; Ron assigns suitable tasks and the final split. Catherine (牛慧) delivers food and provides on-site support. Arrival times are to be confirmed; additional practical support remains open as needed. These confirmations apply only to the listed dates.
- Friday, October 16 — actual participation: Ron led the exterior-board installation. George (耀基) and Adam worked together on reinforcement; Jacob (曲华), Sarah (小滨), Luke and Ken Fong (嘉辉) also came to help. Ericson helped repair the security system. Peggy cleaned the site; Thian-Peng (添平) and Ally swept and collected leaves at the front entrance. Pastor Kaan came in the early afternoon and cooked the crew’s meal; Yi Kiu (二娇) brought a tart. Everyone helped with the final cleanup, leaving the venue ready for Saturday’s Cantonese worship and 5L2F.
Work sequence and timing
- First: strengthen and complete the outside faces of the rooms: Strengthen the framing and connections before installing the previously stained/painted boards. Progress door work where feasible; Ron will confirm the two doorway openings he mentioned.
- Electrical dependency: The electrical team’s timing is outside Ron’s direct control. Coordinate their work and access before closing the interior walls.
- Then: interior finishing: Interior boards/drywall, surface finishing and painting follow electrical work. Ron will confirm the detailed finishing sequence.
- Working estimate, not a deadline: Ron estimated roughly two more weeks overall, including about a week of finishing after electrical work is complete. Electrical progress and the actual work determine the dates; take the time to do the work properly.
- Friday cleanup and weekend activities: Everyone helped clean up on Friday, October 16, leaving the venue ready for Saturday’s Cantonese worship and 5L2F. Saturday construction is not scheduled; any work must be agreed separately around church activities. Sunday, October 18, is a rest day.
- Thanksgiving break: No construction on Sunday, October 11, or Monday, October 12. Work resumes Tuesday.
Youth Scripture-writing activity — to coordinate
Ron agreed in principle that young people may write Scripture with markers on approved interior framing before it is covered, and photograph it as a record. Coordinate the surfaces and timing with Ron. Participants must be supervised in a separate safe area, away from hazardous construction activity. No activity time is booked yet.
Before each Week 2 session
- Confirm attendance for the specific date and role; do not carry last week’s availability forward.
- Ron confirms tasks, measurements, materials/tools and safe assignments. Coordinate electrical access before interior closure.
- Confirm finish times, Wednesday–Friday start times, and building opening/locking arrangements separately from support roles.
- Arrange practical support, food or photos only when people confirm. Keep support separate from the construction count and retain any lifting restrictions.
- Friday’s cleanup for Saturday activities is complete. Keep floor protection in place unless a change is agreed.
- Coordinate the youth Scripture-writing opportunity safely before the framing is covered.
Week 1 · October 4–10
Week 1 archive — October 4–10
The following is the previous week’s confirmed schedule, retained for reference. Its staffing target was four helpers besides Ron; historical gaps are not current recruitment needs.
| Date and time | Plan | Confirmed helpers | Other support | Still needed |
|---|---|---|---|---|
| Sun, Oct 4 2:00 pm | Plan: Ron purchases supplies; Frank helps with purchasing and Jim Fang helps load and unload. | Confirmed helpers: Frank (purchase support) Jim Fang (方健, loading/unloading) | Other support: — | Still needed: Covered |
| Mon, Oct 5 5:30–9:30 pm | Plan: Installation, led by Ron | Confirmed helpers: 嘉辉 Phoenix Phoenix's dad | Other support: Pastor Philip · on-site support Lily · refreshments and photos Peggy · cleanup (time to confirm) | Still needed: 1 more |
| Tue, Oct 6 5:30–9:30 pm | Plan: Installation, led by Ron | Confirmed helpers: Adam · engineering / load-bearing review 嘉辉 李强 Alex Chan Pastor Philip | Other support: Catherine · food and photos Jacqueline · light-duty support (no heavy lifting) | Still needed: Covered |
| Wed, Oct 7 5:30–9:30 pm | Plan: Installation, led by Ron | Confirmed helpers: Adam · engineering / load-bearing review 嘉辉 邓集 Bin Yang 杨滨 | Other support: Jacqueline · light-duty support (no heavy lifting) 霞姐 · food | Still needed: Covered |
| Thu, Oct 8 5:30–9:30 pm | Plan: Installation, led by Ron | Confirmed helpers: Adam · engineering / load-bearing review 嘉辉 邓集 James Enoch Tim Nikki Joanne David Chan | Other support: Sinnie · light-duty support (no heavy lifting) Rose · light meal Cecilia · light meal Shiny · light meal | Still needed: Covered |
| Fri, Oct 9 5:30–9:30 pm | Plan: Installation, led by Ron | Confirmed helpers: Adam · engineering / load-bearing review 嘉辉 David Chan Enoch Sarah (小滨) | Other support: Sinnie · light-duty support (no heavy lifting) Rose · on-site support 霞姐 · food (delivered by Adam) Amy · food; delivery after 6 pm (approx.) Judy · additional photos and on-site support Janet · additional photos and on-site support | Still needed: Covered |
| Sat, Oct 10 4:30–9:30 pm | Plan: Continue installation, led by Ron. Construction is expected to stop around 8:30 pm, then cleanup for Sunday worship. Leave the floor protection in place. | Confirmed helpers: Frank Lei Zhou (周蕾) Jim Fang (方健) Enoch Sarah (小滨) | Other support: Peggy · cleanup after construction (arrival to confirm) | Still needed: Covered |
Week 1 people and responsibilities
- Installation lead: Ron. He directs the work and decides what can be done safely each night.
- Engineering: Adam, October 6–9. His primary focus is reviewing structural support and load-bearing considerations with Ron.
- Confirmed build helpers: 嘉辉, October 5–9; 李强, Alex Chan and Pastor Philip, October 6; 邓集, October 7–8; Bin Yang 杨滨, October 7; David Chan, October 8–9; James, October 8; Phoenix and Phoenix's dad, October 5; Enoch, October 8–10; Tim, Nikki and Joanne, October 8; Sarah (小滨), October 9–10; Frank, Lei Zhou (周蕾) and Jim Fang (方健), October 10.
- On-site support: Pastor Philip, October 5; Jacqueline, October 6–7; Sinnie, October 8–9; Rose, October 9; Judy and Janet, October 9 (photos and on-site support). Jacqueline and Sinnie help with light duties only, with no heavy lifting. Ron directs installation; building access arrangements are to be confirmed separately.
- Food and photos: Lily, October 5; Catherine, October 6; 霞姐, October 7 and 9 (food); Judy and Janet, October 9 (additional photos). Rose, Cecilia and Shiny provide a light meal on October 8. Amy prepares food for October 9 and delivers it after 6 pm (approx.); Adam also brings the food prepared by 霞姐 to church.
- Cleanup: Peggy, Monday, October 5, and Saturday, October 10. Saturday cleanup follows construction, which is expected to stop around 8:30 pm, to prepare for Sunday worship. Her arrival time is to be confirmed. Leave the floor protection in place.
- Daily crew target: Four build helpers each evening, in addition to Ron. Food, photos, cleanup and other support roles do not count toward this target.
Background: Sanctuary Rooms Build Team.
第三周 · 2026 年 10 月 19–23 日
同心建造,一步一步往前。
墙面最后加固及外侧木板安装已完成。10 月 20 日(周二)已安装一间房间的天花板石膏板;墙面最后加固、外侧木板及两间房间的天花板石膏板安装已完成。10 月 21 日(周三)由荣强弟兄带领团队继续天花板石膏板工作。完成较困难的另一间房间天花板。10 月 22 日(周四)由荣强弟兄带领团队安装隔音材料及墙面石膏板。
状态:墙面最后加固及外侧木板安装已完成;杜加坤弟兄已确认 10 月 22 日(周四)切板。邓集已确认 10 月 19、21、22 日协助安装,每天 17:30–21:00。Ken(嘉辉)已确认 10 月 19、20、21、23 日(周一、周二、周三及周五)担任施工帮手,具体分工由荣强确认。Adam 已确认 10 月 20–23 日(周二至周五)担任施工帮手,具体分工由荣强确认。周一至周四施工帮手人数已齐。George(耀基)也已确认 10 月 20 日(周二)担任施工帮手,继续协助尚余工作;具体分工由荣强确认。Gabriel 10 月 20 日(周二)已参与协助安装,并已确认 10 月 21 日(周三)继续协助。施工空缺:周五 1 位。实际支援岗位另计,均可报名。
最后更新:2026 年 10 月 2021 日。
一起记得建造背后的盼望
在一项项工作中,愿我们记得:让年轻家庭照顾孩子时,仍能与会众一同敬拜;减少父母和祖辈抱着孩子上下楼的负担;也让不同事工共享空间。盼望我们把欢迎和关爱化为行动,跨代同行,一同敬拜。

建设进度一览
10 月 2021 日更新:墙面最后加固及外侧木板安装已完成;周三继续天花板石膏板工作。两间房间的天花板石膏板均已安装。周四接着安装隔音材料及墙面石膏板;接缝、表面处理及油漆仍未完成。
已达到的里程碑
- 房间木框架已搭起基本木框架已就位。
- 外侧木板已刷好弟兄姊妹已预备好木板;外侧木板安装现已完成。
- 已增设连接加固第二周已加装连接件,加强部分结构与墙面的连接。
- 墙面最后加固已完成与墙面的最后加固已完成。
- 外侧木板安装已完成已刷好外侧木板的安装已完成。
一间房间天花板石膏板已安装两间房间天花板石膏板均已安装10 月 20日(周二)已安装一间房间的天花板石膏板;不代表所有石膏板收尾工作已完成。日安装第一间;10 月 21 日完成较困难的另一间。石膏板接缝及表面处理仍未完成。
进行中 · 周三重点
继续天花板石膏板工作灯光开关已调低10 月 21 日:Alexander 回应 George(耀基)的建议,按无障碍要求调低灯光开关。
下一步 · 周四重点
- 安装隔音材料计划 10 月 22 日(
周三):由荣强弟兄带领团队继续天花板石膏板工作。周四)先放置隔音材料,再封墙面石膏板。 - 安装墙面石膏板计划 10 月 22 日(周四)在隔音材料之后安装,由荣强确认工序。
接下来要完成
- 玻璃窗及门安装房间玻璃窗和门。
- 通往门厅的新门洞开出计划中通往门厅的新门口。
隔音材料封墙前放置隔音材料。- 石膏板及油漆
继续其余石膏板安装、处理接缝及表面,两间天花板石膏板已安装。周四计划安装墙面石膏板,之后仍需处理接缝及表面,再上漆。10 月 20 日已安装一间房间的天花板石膏板。 - 灯具及开关
完成照明及开关安装。灯光开关已按无障碍高度要求调低;其余灯具及开关工作仍待完成。 - 通风设备安装通风设备,协调电源、气流及风管路线。
- 电视及小音箱为家长及小组使用,安装电视和小音箱。
- 影音网络及布线完成影音、网络连接及相关布线。
封墙前先协调:电线、影音网络及通风路线,再安排隔音材料及石膏板。具体工序由荣强与相关有经验的帮手确认。以上是项目尚余工作,不代表承诺在第三周全部完成。
第三周 · 帮手报名岗位
沿用按岗位配搭的方式:除荣强以外,3 位施工帮手,另按需要安排约 2–3 位实际支援人员。工作推进时,由荣强安排合适分工。George 占周一其中 1 个施工帮手岗位。
即使当晚人手已齐,愿意参与仍然欢迎。每天参与都是自愿的,可参与部分时段,也可轮替;请顾及家庭、团契及休息。
| 日期及时间 | 工作重点 | 已确认施工帮手 | 实际支援 | 待报名施工岗位 |
|---|---|---|---|---|
| 10 月 19 日(周一)开始及结束时间待确认 | 工作重点:George 专注完成与墙面的加固;荣强弟兄带领团队安装剩余已刷好的外侧木板。 | 已确认帮手:George(耀基) 完成与墙面的加固邓集 协助安装 17:30–21:00Ken(嘉辉) 施工帮手 · 具体分工由荣强安排 | 实际支援:材料搬运/现场整理 骏飞传道餐食预备 Dennis & Amy Lily 师母 | 待报名岗位:人手已齐包括切板/材料预备在内的具体分工,由荣强确认。 |
| 10 月 20 日(周二)开始及结束时间待确认 | 工作重点:墙面最后加固及外侧木板安装已完成;已安装一间房间的天花板石膏板。 | 已确认帮手:Adam 施工帮手 · 具体分工由荣强安排George(耀基) 施工帮手 · 具体分工由荣强安排Ken(嘉辉) 施工帮手 · 具体分工由荣强安排Gabriel 协助安装 · 已参与 | 实际支援:材料搬运/现场整理 可报名餐食预备 Vincent & Monica 计划烤一些牛肉、猪排和鸡肉。小食预备 霞姐 · 一份小食 | 待报名岗位:人手已齐工作包括切板/材料预备及协助安装,具体分工由荣强确认。 |
| 10 月 21 日(周三)开始及结束时间待确认 | 工作重点: | 已确认帮手:邓集 协助安装 17:30–21:00Adam 施工帮手 · 具体分工由荣强安排Ken(嘉辉) 施工帮手 · 具体分工由荣强安排Gabriel 协助安装 | 实际支援: 加热饭菜,预备水果、沙拉及龙眼茶。电气调整 Alexander 回应 George(耀基)的建议,按无障碍高度要求调低灯光开关。晚餐 使用 10 月 20 日(周二)余下的饭菜。 | 待报名岗位:人手已齐工作包括切板/材料预备及协助安装,具体分工由荣强确认。 |
| 10 月 22 日(周四)开始及结束时间待确认 | 工作重点: | 已确认帮手:杜加坤弟兄 切板/材料预备邓集 协助安装 17:30–21:00Adam 施工帮手 · 具体分工由荣强安排 | 实际支援:材料搬运/现场整理 可报名餐食预备 Catherine(牛慧) | 待报名岗位:人手已齐具体分工由荣强确认。 |
| 10 月 23 日(周五)开始及结束时间待确认 | 工作重点:按进度接续已具备条件的工作;每天工序由荣强确认,需要专门技能的工作另行协调。 | 已确认帮手:Adam 施工帮手 · 具体分工由荣强安排Ken(嘉辉) 施工帮手 · 具体分工由荣强安排 | 实际支援:材料搬运/现场整理 可报名清洁 Peggy Ter Family (戴家) 人手已齐餐食预备 简牧师 | 待报名岗位:还需 1 位施工帮手施工帮手 · 还需 1 位工作包括切板/材料预备及协助安装,具体分工由荣强确认。 |
按需要合计约 2–3 位,岗位可兼任。清洁帮手仅周五需要。欢迎轻量支援,不搬重物。
选一天,选一个岗位。
请联系添平,说明日期、岗位和方便的时段,并说明工具经验或搬运限制。施工与实际支援分开;经确认后才列入名单。
玻璃、电工、通风及结构工作需要合适且有经验的帮手。报名一般施工岗位,不等于可以承担这些工作。由荣强确认安全分工,开门安排另行确认。
此处不新增周末施工;如需做工,须另行确认并协调教会活动。
每次开工前
- 逐日确认出席、开始及结束时间,以及开门锁门安排。
- 由荣强确认合适的工作、工具及当天工序;封墙前协调相关专门工作。
- 确认后才安排餐食及实际支援;轻量支援人员不搬重物。
- 地板保护继续保留,除非另有商定;配合教会活动确认清洁时段。
往周记录
以下保留之前的排班及参与记录;历史人手缺口不是目前招募需求。
第二周 · 10 月 13–16 日
历史计划及岗位确认,包括周五实际参与记录;不是第三周报名名单。
状态: 第二周:周二、周三及周四施工人手已齐。周五实际施工及支援人员已记录在下方。Susan(晓英)周三现场支援;Catherine(牛慧)周四送餐及现场支援。周五清洁已完成,场地已为周六活动预备好。
最后更新: 2026 年 10 月 17 日。
第二周计划于 10 月 13 日至 16 日(周二至周五)施工,由谢荣强带领。周二晚上 5:30 开始,结束时间及其余晚上的时间待确认。这一阶段按岗位分工:除荣强以外,3 位施工帮手,另按需要安排约 2–3 位实际支援人员。即使当晚人手已齐,愿意参与的弟兄姊妹仍然欢迎;具体工作由荣强安排。每天参与都是自愿的,帮手可轮替,不需要每晚都来。
第二周施工时间及名单
| 日期及时间 | 安排 | 已确认施工岗位 | 支援岗位 | 待报名施工岗位 |
|---|---|---|---|---|
| 10 月 13 日(周二) 晚上 5:30 开始;结束待确认 | 安排:先加强框架及连接,再安装已刷好的外侧木板。门的工作由荣强按进度安排。 | 已确认岗位:切板+预钻孔: Adam 和 Gabriel 具体分配由荣强安排。 安装: Ken Fong(嘉辉) | 其他支援:Judy · 现场支援 Janet · 现场支援 Judy · 带一道菜 霞姐 · 带一道菜 | 待报名施工岗位:人手已齐 |
| 10 月 14 日(周三) 晚上;时间待确认 | 安排:先加强框架及连接,再安装已刷好的外侧木板。门的工作由荣强按进度安排。 | 已确认岗位:切板+预钻孔: Adam 和 Gabriel 预钻孔或安装: 邓集 切板、预钻孔及安装,3 位帮手的具体分工由荣强安排。 | 支援岗位:Susan(晓英) · 现场支援:搬运材料、清洁;到场时间待确认 按需要欢迎其他实际支援,合计约 2–3 位。 | 待报名施工岗位:人手已齐 |
| 10 月 15 日(周四)白天 上午 10:00 开门 | 安排:Sean 来布线;白天的安排与晚上施工分开。 | 已确认岗位:Sean · 布线 | 支援岗位:Ericson · 上午 10:00 到教会,为 Sean 开门 | 待报名施工岗位:不适用——白天布线及开门安排 |
| 10 月 15 日(周四) 晚上;时间待确认 | 安排:先加强框架及连接,再安装已刷好的外侧木板。门的工作由荣强按进度安排。 | 已确认岗位:切板: Du Jiakun(杜弟兄) 预钻孔或安装: 邓集 安装: Enoch Zheng(郑以诺) 合适工作及具体分工由荣强安排。 | 支援岗位:Catherine(牛慧) · 送餐 Catherine(牛慧) · 现场支援 材料搬运/现场整理 · 按需要可报名 清洁 · 按需要可报名 按需要合计约 2–3 位支援人员,岗位可兼任;到场时间待确认。 | 待报名施工岗位:人手已齐 |
| 10 月 16 日(周五) 实际参与记录 | 实际工作:继续加固及安装已刷好的外侧木板。George(耀基)和 Adam 配搭加装连接件、加强与墙面的连接,荣强带队安装外侧木板。大家一起清洁,为周六粤语崇拜及五饼二鱼预备好场地。 | 实际到场:施工带领: 谢荣强 加固: George(耀基)和 Adam 其他施工帮手: Jacob(曲华) Sarah(小滨) Luke Ken Fong(嘉辉) | 实际支援:Ericson · 协助修好保安系统 Peggy · 现场清洁 添平和 Ally · 清扫及收集前门落叶 简牧师 · 下午较早到教会,为施工团队做饭 Yi Kiu(二娇) · 带来馅饼 大家一起收拾清洁,为周六粤语崇拜及五饼二鱼预备好场地。 | 施工人手:人手已齐 |
报名空缺岗位:请联系添平,说明日期、岗位和方便的时间,例如“周四——预钻孔”。请说明使用工具的经验或搬运限制,由荣强确认合适的分工并指导。施工和支援分开,支援岗位可兼任;出席确认后再更新名单。
第二周:岗位与配搭方式
- 荣强——施工带领: 荣强负责量尺寸、作决定、安排顺序和安全,并在需要时亲自固定,提高施工效率。帮手按他的尺寸和指示配搭;并非每项工作都能重复照做。
- 切板——1 位: 按荣强量好的尺寸切板,由他安排合适的人并指导;切板帮手可轮替。
- 预钻孔——1 位: 按荣强指定的位置预钻孔,为下一步安装预备。
- 固定/安装——1 位: 按荣强安排协助固定和安装;岗位可随当天工作调整。
- 实际支援——按需要约 2–3 位: 搬运合适的材料、整理现场、清洁及鼓励团队。支援不计入 3 个施工岗位。Jacqueline、Sinnie 等轻量支援人员若参与,不安排搬重物。
- 已确认 10 月 13 日(周二): Adam 和 Gabriel 协助切板及预钻孔,具体分配由荣强安排。Ken Fong(嘉辉)协助荣强安装。Judy 和 Janet 现场支援,Judy 和霞姐各带一道菜。
- 已确认 10 月 14 日(周三): Adam 和 Gabriel 加入切板/预钻孔,邓集协助预钻孔或安装。3 位施工帮手人手已齐,具体岗位分配由荣强安排。Susan(晓英)协助现场支援,包括搬运材料及清洁;到场时间待确认。
- 10 月 15 日(周四)白天开门: Ericson 上午 10:00 到教会,为 Sean 开门布线,与晚上的施工分开。
- 已确认 10 月 15 日(周四): Du Jiakun(杜弟兄)切板;邓集协助预钻孔或安装;Enoch Zheng(郑以诺)协助安装。3 位施工帮手人手已齐,合适工作及具体分工由荣强安排。Catherine(牛慧)送餐及现场支援。到场时间待确认,其他实际支援按需要仍可报名。以上只确认所列日期。
- 10 月 16 日(周五)实际参与: 荣强带队安装外侧木板;George(耀基)和 Adam 配搭加固。Jacob(曲华)、Sarah(小滨)、Luke 和 Ken Fong(嘉辉)也到场帮忙。Ericson 协助修好保安系统。Peggy 清洁现场,添平和 Ally 清扫及收集前门落叶。简牧师下午较早到教会,为施工团队做饭;Yi Kiu(二娇)带来馅饼。大家一起收拾清洁,场地已为周六粤语崇拜及五饼二鱼预备好。
施工顺序与时间预期
- 先加固,再完成房间外侧: 先加强框架及连接,再安装之前已刷好的外侧木板。按进度处理门的工作;荣强提到的两个门洞,具体范围由他确认。
- 电工是后续工作的前提: 电工团队的时间不由荣强直接掌握。封闭内侧墙面前,要协调电工进度及所需施工空间。
- 之后完成室内: 电工完成后,再进行内侧板材/石膏板、表面处理及油漆;具体工序由荣强确认。
- 估计,不是完工承诺: 荣强估计整体可能还需约两周,其中电工完成后,室内收尾约需一周。实际日期取决于电工进度和现场工作;留足时间,把工作做好。
- 周五清洁与周末活动: 10 月 16 日(周五)大家一起收拾清洁,场地已为周六粤语崇拜及五饼二鱼预备好。周六尚未安排施工,如需做工须另行协调教会活动。10 月 18 日(主日)休息。
- 感恩节休息: 10 月 11 日(主日)及 12 日(周一)不施工,周二恢复。
年轻人写经文——另行协调
荣强原则上同意年轻人在内侧框架封板前,用记号笔在获准的位置写经文,并拍照留念。具体位置和时间须与荣强协调。参与者须有人带领,在与危险施工分开的安全区域进行。活动时间尚未安排。
第二周每次开工前
- 逐日确认出席和岗位,不自动沿用上周的可用时间。
- 荣强确认工作、尺寸、材料工具及安全分工;封闭内侧前,协调电工施工空间。
- 确认结束时间、周三至周五开始时间,以及开门锁门安排;支援人员不自动承担开门责任。
- 实际支援、食物和拍照须有人确认才安排;支援与施工人数分开,并保留不搬重物等限制。
- 周五为周六活动预备的清洁已完成。地板保护继续保留,除非另有商定。
- 在封板前,与荣强安全协调年轻人写经文的机会。
第一周 · 10 月 4–10 日
第一周存档——10 月 4 日至 10 日
以下保留上周已确认的排班供参考。当时目标为除荣强以外 4 位帮手;历史缺口不是当前招募需求。
| 日期及时间 | 安排 | 已确认帮手 | 其他支援 | 还需要 |
|---|---|---|---|---|
| 10 月 4 日 下午 2:00 | 安排:荣强采购材料,Frank 协助采购,方健协助装卸。 | 已确认帮手:Frank(采购支援) 方健 Jim Fang(装卸) | 其他支援:— | 还需要:人手已齐 |
| 10 月 5 日 晚上 5:30–9:30 | 安排:安装施工,荣强带领 | 已确认帮手:嘉辉 Phoenix Phoenix 的爸爸 | 其他支援:Pastor Philip · 现场支援 Lily · 茶点、拍照 Peggy · 清洁(时间待确认) | 还需要:还差 1 位 |
| 10 月 6 日 晚上 5:30–9:30 | 安排:安装施工,荣强带领 | 已确认帮手:Adam · 工程/结构承重检查 嘉辉 李强 Alex Chan 骏飞传道 | 其他支援:Catherine · 送吃的、照相 Jacqueline · 轻量支援(不搬重物) | 还需要:人手已齐 |
| 10 月 7 日 晚上 5:30–9:30 | 安排:安装施工,荣强带领 | 已确认帮手:Adam · 工程/结构承重检查 嘉辉 邓集 Bin Yang 杨滨 | 其他支援:Jacqueline · 轻量支援(不搬重物) 霞姐 · 食物 | 还需要:人手已齐 |
| 10 月 8 日 晚上 5:30–9:30 | 安排:安装施工,荣强带领 | 已确认帮手:Adam · 工程/结构承重检查 嘉辉 邓集 James Enoch Tim Nikki Joanne David Chan | 其他支援:Sinnie · 轻量支援(不搬重物) Rose · 简餐 Cecilia · 简餐 Shiny · 简餐 | 还需要:人手已齐 |
| 10 月 9 日 晚上 5:30–9:30 | 安排:安装施工,荣强带领 | 已确认帮手:Adam · 工程/结构承重检查 嘉辉 David Chan Enoch Sarah(小滨) | 其他支援:Sinnie · 轻量支援(不搬重物) Rose · 现场支援 霞姐 · 食物(Adam 带到教会) Amy · 食物,约六点多送到教会 Judy · 额外拍照及现场支援 Janet · 额外拍照及现场支援 | 还需要:人手已齐 |
| 10 月 10 日 下午 4:30 至晚上 9:30 | 安排:继续安装施工,荣强带领。预计晚上 8:30 左右停止施工,随后清洁,为主日敬拜预备。地板保护继续保留,不拆掉。 | 已确认帮手:Frank Lei Zhou(周蕾) Jim Fang(方健) Enoch Sarah(小滨) | 其他支援:Peggy · 施工后清洁(到场时间待确认) | 还需要:人手已齐 |
第一周人员与分工
- 安装负责人:荣强。他指挥施工,并决定每晚哪些工作可以安全进行。
- 工程:Adam,10 月 6 日至 9 日。主要与荣强一起检查结构支撑及承重方面的事项。
- 已确认的施工帮手:嘉辉,10 月 5 日至 9 日;李强、Alex Chan 和骏飞传道,10 月 6 日;邓集,10 月 7、8 日;Bin Yang 杨滨,10 月 7 日;David Chan,10 月 8、9 日;James,10 月 8 日;Phoenix 和 Phoenix 的爸爸,10 月 5 日;Enoch,10 月 8 日至 10 日;Tim、Nikki 和 Joanne,10 月 8 日;Sarah(小滨),10 月 9、10 日;Frank、Lei Zhou(周蕾)和 Jim Fang(方健),10 月 10 日。
- 现场支援:Pastor Philip,10 月 5 日;Jacqueline,10 月 6、7 日;Sinnie,10 月 8、9 日;Rose,10 月 9 日;Judy 和 Janet,10 月 9 日(拍照及现场支援)。Jacqueline 和 Sinnie 协助轻量工作,不搬重物。安装工作由荣强指挥;开门安排另行确认。
- 食物及拍照:Lily,10 月 5 日;Catherine,10 月 6 日;霞姐,10 月 7、9 日(食物);Judy 和 Janet,10 月 9 日(额外拍照支援)。Rose、Cecilia 和 Shiny 于 10 月 8 日提供简餐。Amy 于 10 月 9 日准备食物,约六点多送到教会;Adam 也会将霞姐预备的食物带到教会。
- 清洁:Peggy 于 10 月 5 日(周一)及 10 月 10 日(周六)协助清洁。周六预计晚上 8:30 左右停止施工,随后清洁,为主日敬拜预备。她的到场时间待确认。地板保护继续保留,不拆掉。
- 每晚人数:除荣强以外,目标是每晚 4 位施工帮手;更多帮手可轮替休息。食物、拍照、清洁及其他支援岗位不计入此人数。
背景:主堂房间施工团队.