Schedule

WEEK 4 · OCTOBER 26–30, 2026

Building together, one step at a time.

October 27: window-side frame reinforcement is complete. Ron worked with Ken Fong (嘉辉), Adam, Qiang Li (李强) and Gabriel; Catherine (牛慧), 涵之 and Pastor Julia prepared the meal. The plan for October 28 is to install the remaining wall drywall.

Status:Tuesday, October 27: Ron worked with Ken Fong (嘉辉), Adam, Qiang Li (李强) and Gabriel. Catherine (牛慧), 涵之 and Pastor Julia prepared the meal. Window-side frame reinforcement is complete. Wednesday, October 28: Roy and Deng Ji (邓集) are confirmed to help Ron install the remaining wall drywall; one more construction helper is needed. Vincent and Monica will provide food, with Vincent delivering a little after 4 pm. Thursday, October 29: Roy, Qiang Li, Ken Fong, Adam and Deng Ji are confirmed; the helper headcount is covered. Pastor Kaan will prepare food; Peggy is confirmed for cleanup, with timing to confirm. Friday, October 30 is off for rest; no construction or cleanup shift is scheduled.

Last updated: October 27, 2026.

Keep the purpose in view

As we build, our hope is to help young families stay connected to worship, reduce stair trips for parents and grandparents caring for children, and share the space across ministries. We are putting welcome and care into practice, across generations.

Chinese–English infographic: two sanctuary rooms supporting young families in worship, reducing stair use, and providing shared ministry space.
View full-size infographic · Tap or click the image to read and zoom.

Progress so far

Updated October 27: window-side frame reinforcement is complete. Wall drywall installation started October 26, with about half installed that evening. The plan for October 28 is to install the remaining wall drywall; joint and surface finishing and paint remain.

Milestones reached

  • Room framing assembledThe basic wood frames are in place.
  • Stained boards preparedVolunteers prepared the stained/painted boards; exterior installation is now complete.
  • Further connections reinforcedAdditional brackets and stronger wall connections were added in Week 2.
  • Wall reinforcement completeFinal reinforcement to the wall is complete.
  • Exterior stained boards installedInstallation of the stained exterior-facing boards is complete.
  • Both rooms’ ceiling drywall installedFirst room installed October 20; the more difficult second room finished October 21. Drywall joint and surface finishing remain.
  • Light switches loweredOctober 21: Alexander addressed George’s suggestion by lowering the light switches for accessibility.
  • Sound-insulation panels installedOctober 23: with the right cutting tool, Ron, Adam, Ken Fong (嘉辉), Phoenix (小毛) and Phoenix’s dad installed the panels.
  • Window-side frame reinforcedOctober 27: reinforcement on the window side of the frame was completed before installing the remaining drywall.

Next · Week 4 planning

  • Wall drywall and remaining workOctober 28 plan: install the remaining wall drywall after completing the window-side frame reinforcement. Ron confirms suitable assignments.
  • Thursday cleanup · Friday restPeggy is confirmed for cleanup October 29; timing to confirm. No construction or cleanup shift October 30.

Still ahead

  • Glass windows and doorsInstall the room windows and doors.
  • New door openings to the foyerCreate the planned new doorway exits to the foyer.
  • Drywall and paintBoth ceilings and the sound-insulation panels are installed. Wall drywall installation is underway; the remaining boards, joint and surface finishing and paint still need completion.
  • Lighting and switchesLight switches have been lowered to address accessibility height requirements; the remaining lighting and switch work still needs completion.
  • VentilationInstall ventilation; coordinate power, airflow and the duct route.
  • TV and small speakersMount the TV and small speakers for parents and small-group use.
  • AV network and wiringComplete the AV/network connections and wiring.

Before closing the walls: Confirm the remaining electrical, AV/network and ventilation routes with the relevant skilled helpers. Window-side frame reinforcement is complete; the October 28 plan is to install the remaining wall drywall. This is the remaining project scope, not a promise to finish everything in Week 4.

Week 4 · helper slots

Week 4 is a placeholder plan: retain the current target of three construction helpers besides Ron, with about 2–3 practical-support people as needed. Daily tasks, times and remaining attendance still need confirmation; no previous-week availability is carried forward.

Everyone is welcome to take part, even when a shift is covered. Participation is voluntary; partial evenings and rotation are welcome. Please keep time for family, fellowship and rest.

Date and timeWork focusConfirmed build helpersPractical supportOpen build slots
Mon, Oct 265:30–9:30 pmWork focus: Placeholder: work plan and suitable assignments to confirm with Ron.Confirmed helpers: Ken Fong (嘉辉)
Build helper · tasks assigned by Ron
Qiang Li (李强)
Build helper · tasks assigned by Ron
Fang Jian (方健)
Build helper · tasks assigned by Ron
Zhou Lei (周磊)
Build helper · tasks assigned by Ron
Support: Materials / site organization
Unassigned
On-site support
Pastor Philip (骏飞传道)
Food
Lily · preparing and delivering dinner
Open build slots: CoveredRon assigns suitable tasks.
Tue, Oct 27Reported participationWork focus: Completed reinforcement on the window side of the frame before installing the remaining drywall.Attended: Ken Fong (嘉辉)
Build helper · attended
Adam
Build helper · attended
Qiang Li (李强)
Build helper · attended
Gabriel
Build helper · attended
Support: Food
Catherine (牛慧), 涵之 & Pastor Julia · meal preparation
Open build slots: CoveredReported participation recorded.
Wed, Oct 28Times to confirmWork focus: Plan: install the remaining wall drywall following completion of the window-side frame reinforcement.Confirmed helpers: Roy
Build helper · tasks assigned by Ron
Deng Ji (邓集)
Build helper · tasks assigned by Ron
Support: Materials / site organization
Unassigned
Food
Vincent & Monica
Monica: pork rib soup; Vincent: roast beef and chicken, plus bread.
Vincent delivering a little after 4 pm.
Open build slots: 1 moreBuild assistance · 1 open; assignments to confirm
Thu, Oct 29Times to confirmWork focus: Placeholder: work plan and suitable assignments to confirm with Ron. Cleanup after construction; timing to confirm.Confirmed helpers: Roy
Build helper · tasks assigned by Ron
Qiang Li (李强)
Build helper · tasks assigned by Ron
Ken Fong (嘉辉)
Build helper · tasks assigned by Ron
Adam
Build helper · tasks assigned by Ron
Deng Ji (邓集)
Build helper · tasks assigned by Ron
Support: Materials / site organization
Unassigned
Food
Pastor Kaan · preparing food
Thursday cleanup
Peggy · timing to confirm
Open build slots: CoveredRon assigns suitable tasks.
Fri, Oct 30Rest day · no shiftWork focus: Off for rest. No construction or cleanup shift.Confirmed helpers: Not applicableSupport: No shiftOpen build slots: Not applicable · rest day

Support roles are separate from construction. Peggy is confirmed for Thursday cleanup; timing remains to be confirmed. Friday is off for rest. Light-duty support is welcome, with no heavy lifting.

Glass, electrical, ventilation and structural work need suitable skilled helpers. Ron confirms safe assignments; building access is arranged separately. No weekend shift is scheduled.

Before each work session

  1. Confirm that date’s attendance, start/finish times and opening/locking arrangements.
  2. Ron confirms suitable tasks, tools and the day’s sequence. Coordinate specialist work before closing walls.
  3. Arrange food and practical support only after confirmation. Light-duty helpers must not lift heavy items.
  4. Keep floor protection in place unless a change is agreed. Peggy is confirmed for Thursday, October 29 cleanup; confirm timing. Friday, October 30 is off for rest.

Previous weeks

Earlier schedules and participation records are kept below. Historical staffing gaps are not current recruitment needs.

Week 3 · October 19–23

Historical schedule and reported participation. Earlier entries retain their recorded confirmation status; this is not the Week 4 signup list. Friday’s insulation installation, crew, cleanup and meal are recorded below. Ron led the work; Phoenix and her dad responded to Thursday evening’s call for helpers.

Date and timeWork focusConfirmed build helpersPractical supportOpen build slots
Mon, Oct 19Times to confirmWork focus: George focuses on final wall reinforcement. Brother Ron leads the crew installing the remaining stained exterior-facing boards.Confirmed helpers: George (耀基)
Final wall reinforcement
邓集
Assist in installation
5:30–9:00 pm
Ken Fong (嘉辉)
Build helper · tasks assigned by Ron
Support: Materials / site organization
Pastor Philip
Food preparation
Dennis & Amy
Lily 师母
Open build slots: CoveredRon confirms task assignments, including cutting / preparation.
Tue, Oct 20Times to confirmWork focus: Wall reinforcement and exterior stained-board installation completed. Ceiling drywall installed in one room.Confirmed helpers: Adam
Build helper · tasks assigned by Ron
George (耀基)
Build helper · tasks assigned by Ron
Ken Fong (嘉辉)
Build helper · tasks assigned by Ron
Gabriel
Assist in installation · attended
Support: Materials / site organization
Open
Food preparation
Vincent & Monica
Plan to prepare roasted beef, pork chops and chicken.
Snack preparation
Ha Jie (霞姐) · A snack
Open build slots: CoveredTasks include cutting / preparation and installation; Ron confirms the assignments.
Wed, Oct 21Times to confirmWork focus: Finished ceiling drywall in the second room, the more difficult section. Alexander lowered the light switches following George’s suggestion to address accessibility height requirements.Confirmed helpers: 邓集
Assist in installation
5:30–9:00 pm
Adam
Build helper · tasks assigned by Ron
Ken Fong (嘉辉)
Build helper · tasks assigned by Ron
Gabriel
Assist in installation
Support: Kitchen support
Janet & Judy
Heated food; prepared fruit, salad and longan tea.
Electrical adjustment
Alexander
Lowered the light switches following George’s suggestion to address accessibility height requirements.
Dinner
Leftovers from Tuesday, October 20.
Open build slots: CoveredTasks include cutting / preparation and installation; Ron confirms the assignments.
Thu, Oct 22Times to confirmWork focus: Made progress on sound insulation work; the team still needs suitable tools to cut the acoustic insulation panels.Attended: Adam
Build helper · attended
Jim Deng (邓集)
Build helper · attended
Brother Du (杜加坤)
Build helper · attended
Ken Fong (嘉辉)
Build helper · attended
Support: Materials / site organization
Open
Food preparation
Catherine (牛慧)
Open build slots: CoveredRon confirms task assignments.
Fri, Oct 23Actual participationWork completed: Sound-insulation panels installed with the right cutting tool, led by Ron.Attended: Adam
Sound-insulation installation
Ken Fong (嘉辉)
Sound-insulation installation
Phoenix (小毛)
Sound-insulation installation
Phoenix’s dad
Sound-insulation installation
Support provided: Cleanup
Peggy & Ally
Meal preparation
Pastor Kaan · home-style meal for the crew
Construction coverage: Covered
Week 2 · October 13–16

Historical plan and role confirmations, including Friday’s reported actual participation. This is not the Week 3 signup list.

Status: Week 2: Tuesday, Wednesday and Thursday construction roles are covered. Friday’s actual construction and support participants are recorded below. Susan (晓英) provides Wednesday on-site support; Catherine (牛慧) delivers food and provides Thursday on-site support. Friday’s cleanup is complete for Saturday’s activities.
Last updated: October 17, 2026.

Week 2 is planned for Tuesday–Friday, October 13–16, led by Ron Xie (谢荣强). Tuesday starts at 5:30 pm; its finish time and the remaining evenings’ times are to be confirmed. The focused roles are covered by three build helpers alongside Ron, plus about two or three people for practical support as needed. Everyone is welcome to take part, even when a shift is covered; tasks will be assigned by Ron. Participation is voluntary on every workday, and helpers can rotate rather than attend every evening.

Week 2 schedule and crew

Date and timePlanAssigned construction rolesSupport rolesOpen construction roles
Tue, Oct 13
5:30 pm start; finish to confirm
Plan: Strengthen framing/connections, then install the stained exterior-facing boards. Door work as directed by Ron.Assigned roles: Cutting + pre-drilling:
Adam and Gabriel
Ron assigns the split.
Installation:
Ken Fong (嘉辉)
Other support: Judy · on-site support
Janet · on-site support
Judy · bringing a dish
Ha Jie (霞姐) · bringing a dish
Open construction roles: Covered
Wed, Oct 14
Evening; time to confirm
Plan: Strengthen framing/connections, then install the stained exterior-facing boards. Door work as directed by Ron.Assigned roles: Cutting + pre-drilling:
Adam and Gabriel
Pre-drilling or installation:
邓集
Ron assigns the three helpers across cutting, pre-drilling and installation.
Support roles: Susan (晓英) · on-site support: moving materials and cleaning; arrival time to confirm
Additional practical support welcome as needed; about 2–3 support people in total.
Open construction roles: Covered
Thu, Oct 15 — daytime
10:00 am access
Plan: Sean comes for wiring. This daytime visit is separate from the evening construction shift.Assigned roles: Sean · wiringSupport roles: Ericson · arrives at 10:00 am to give Sean access to the churchOpen construction roles: Not applicable — daytime wiring/access visit
Thu, Oct 15
Evening; time to confirm
Plan: Strengthen framing/connections, then install the stained exterior-facing boards. Door work as directed by Ron.Assigned roles: Cutting:
Du Jiakun
Pre-drilling or installation:
邓集
Installation:
Enoch Zheng (郑以诺)
Ron assigns suitable tasks and the final split.
Support roles: Catherine (牛慧) · food delivery
Catherine (牛慧) · on-site support
Materials / on-site organization · Open as needed
Cleanup · Open as needed
About 2–3 support people in total, as needed; tasks can be combined. Arrival times to confirm.
Open construction roles: Covered
Fri, Oct 16
Actual participation
Work completed: Continued reinforcement and installation of the stained exterior-facing boards. George and Adam worked on brackets and stronger wall connections while Ron led the board installation. The team cleaned up for Saturday’s Cantonese worship and 5L2F.Attended: Work lead:
Ron Xie (谢荣强)
Reinforcement:
George (耀基) and Adam
Other build helpers:
Jacob (曲华)
Sarah (小滨)
Luke
Ken Fong (嘉辉)
Support provided: Ericson · helped repair the security system
Peggy · site cleaning
Thian-Peng (添平) and Ally · swept and collected leaves at the front entrance
Pastor Kaan · came in the early afternoon and cooked the crew’s meal
Yi Kiu (二娇) · brought a tart
Everyone helped with the final cleanup for Saturday’s Cantonese worship and 5L2F.
Construction coverage: Covered

Sign up for an open role: Contact Thian-Peng with the date, role, and times you can help (for example, “Thursday — pre-drilling”). Let us know your tool experience or any lifting restrictions. Ron confirms suitable assignments and provides guidance. Construction and support are separate; a support volunteer may combine tasks. The roster is updated after attendance is confirmed.

Week 2: roles and expectations

  • Ron — work lead: Ron measures, makes decisions, directs the sequence and safety, and carries out fastening where his experience keeps the work moving. Helpers follow his measurements and instructions; not every task is repetitive.
  • Cutting — 1 helper: Cut boards to Ron’s measurements. Ron assigns a suitable helper and provides guidance; cutters may rotate.
  • Pre-drilling — 1 helper: Prepare the holes Ron identifies so the next installation step can proceed.
  • Fastening / installation — 1 helper: Assist Ron with fastening and installation as directed. Roles may flex with the task.
  • Practical support — about 2–3 people, as needed: Move suitable materials, keep things organized, clean up, and encourage the team. Support is separate from the three construction positions. Light-duty volunteers, including Jacqueline and Sinnie if they join, must not lift heavy items.
  • Confirmed for Tuesday, October 13: Adam and Gabriel help with cutting and pre-drilling; Ron assigns the split. Ken Fong (嘉辉) assists Ron with installation. Judy and Janet provide on-site support; Judy and Ha Jie (霞姐) each bring a dish.
  • Confirmed for Wednesday, October 14: Adam and Gabriel join for cutting/pre-drilling, alongside 邓集 for pre-drilling or installation. The three-helper crew is covered; Ron assigns the final split across the construction roles. Susan (晓英) provides on-site support with moving materials and cleaning. Her arrival time is to be confirmed.
  • Thursday daytime access, October 15: Ericson arrives at 10:00 am to give Sean access for wiring. This is separate from the evening construction shift.
  • Confirmed for Thursday, October 15: Du Jiakun handles cutting; 邓集 helps with pre-drilling or installation; Enoch Zheng (郑以诺) assists with installation. The three construction-helper roles are covered; Ron assigns suitable tasks and the final split. Catherine (牛慧) delivers food and provides on-site support. Arrival times are to be confirmed; additional practical support remains open as needed. These confirmations apply only to the listed dates.
  • Friday, October 16 — actual participation: Ron led the exterior-board installation. George (耀基) and Adam worked together on reinforcement; Jacob (曲华), Sarah (小滨), Luke and Ken Fong (嘉辉) also came to help. Ericson helped repair the security system. Peggy cleaned the site; Thian-Peng (添平) and Ally swept and collected leaves at the front entrance. Pastor Kaan came in the early afternoon and cooked the crew’s meal; Yi Kiu (二娇) brought a tart. Everyone helped with the final cleanup, leaving the venue ready for Saturday’s Cantonese worship and 5L2F.

Work sequence and timing

  • First: strengthen and complete the outside faces of the rooms: Strengthen the framing and connections before installing the previously stained/painted boards. Progress door work where feasible; Ron will confirm the two doorway openings he mentioned.
  • Electrical dependency: The electrical team’s timing is outside Ron’s direct control. Coordinate their work and access before closing the interior walls.
  • Then: interior finishing: Interior boards/drywall, surface finishing and painting follow electrical work. Ron will confirm the detailed finishing sequence.
  • Working estimate, not a deadline: Ron estimated roughly two more weeks overall, including about a week of finishing after electrical work is complete. Electrical progress and the actual work determine the dates; take the time to do the work properly.
  • Friday cleanup and weekend activities: Everyone helped clean up on Friday, October 16, leaving the venue ready for Saturday’s Cantonese worship and 5L2F. Saturday construction is not scheduled; any work must be agreed separately around church activities. Sunday, October 18, is a rest day.
  • Thanksgiving break: No construction on Sunday, October 11, or Monday, October 12. Work resumes Tuesday.

Youth Scripture-writing activity — to coordinate

Ron agreed in principle that young people may write Scripture with markers on approved interior framing before it is covered, and photograph it as a record. Coordinate the surfaces and timing with Ron. Participants must be supervised in a separate safe area, away from hazardous construction activity. No activity time is booked yet.

Before each Week 2 session

  1. Confirm attendance for the specific date and role; do not carry last week’s availability forward.
  2. Ron confirms tasks, measurements, materials/tools and safe assignments. Coordinate electrical access before interior closure.
  3. Confirm finish times, Wednesday–Friday start times, and building opening/locking arrangements separately from support roles.
  4. Arrange practical support, food or photos only when people confirm. Keep support separate from the construction count and retain any lifting restrictions.
  5. Friday’s cleanup for Saturday activities is complete. Keep floor protection in place unless a change is agreed.
  6. Coordinate the youth Scripture-writing opportunity safely before the framing is covered.
Week 1 · October 4–10

Week 1 archive — October 4–10

The following is the previous week’s confirmed schedule, retained for reference. Its staffing target was four helpers besides Ron; historical gaps are not current recruitment needs.

Date and timePlanConfirmed helpersOther supportStill needed
Sun, Oct 4
2:00 pm
Plan: Ron purchases supplies; Frank helps with purchasing and Jim Fang helps load and unload.Confirmed helpers: Frank (purchase support)
Jim Fang (方健, loading/unloading)
Other support: —Still needed: Covered
Mon, Oct 5
5:30–9:30 pm
Plan: Installation, led by RonConfirmed helpers: 嘉辉
Phoenix (小毛)
Phoenix's dad
Other support: Pastor Philip · on-site support
Lily · refreshments and photos
Peggy · cleanup (time to confirm)
Still needed: 1 more
Tue, Oct 6
5:30–9:30 pm
Plan: Installation, led by RonConfirmed helpers: Adam · engineering / load-bearing review
嘉辉
李强
Alex Chan
Pastor Philip
Other support: Catherine · food and photos
Jacqueline · light-duty support (no heavy lifting)
Still needed: Covered
Wed, Oct 7
5:30–9:30 pm
Plan: Installation, led by RonConfirmed helpers: Adam · engineering / load-bearing review
嘉辉
邓集
Bin Yang 杨滨
Other support: Jacqueline · light-duty support (no heavy lifting)
霞姐 · food
Still needed: Covered
Thu, Oct 8
5:30–9:30 pm
Plan: Installation, led by RonConfirmed helpers: Adam · engineering / load-bearing review
嘉辉
邓集
James
Enoch
Tim
Nikki
Joanne
David Chan
Other support: Sinnie · light-duty support (no heavy lifting)
Rose · light meal
Cecilia · light meal
Shiny · light meal
Still needed: Covered
Fri, Oct 9
5:30–9:30 pm
Plan: Installation, led by RonConfirmed helpers: Adam · engineering / load-bearing review
嘉辉
David Chan
Enoch
Sarah (小滨)
Other support: Sinnie · light-duty support (no heavy lifting)
Rose · on-site support
霞姐 · food (delivered by Adam)
Amy · food; delivery after 6 pm (approx.)
Judy · additional photos and on-site support
Janet · additional photos and on-site support
Still needed: Covered
Sat, Oct 10
4:30–9:30 pm
Plan: Continue installation, led by Ron. Construction is expected to stop around 8:30 pm, then cleanup for Sunday worship. Leave the floor protection in place.Confirmed helpers: Frank
Lei Zhou (周磊)
Jim Fang (方健)
Enoch
Sarah (小滨)
Other support: Peggy · cleanup after construction (arrival to confirm)Still needed: Covered

Week 1 people and responsibilities

  • Installation lead: Ron. He directs the work and decides what can be done safely each night.
  • Engineering: Adam, October 6–9. His primary focus is reviewing structural support and load-bearing considerations with Ron.
  • Confirmed build helpers: 嘉辉, October 5–9; 李强, Alex Chan and Pastor Philip, October 6; 邓集, October 7–8; Bin Yang 杨滨, October 7; David Chan, October 8–9; James, October 8; Phoenix (小毛) and Phoenix's dad, October 5; Enoch, October 8–10; Tim, Nikki and Joanne, October 8; Sarah (小滨), October 9–10; Frank, Lei Zhou (周磊) and Jim Fang (方健), October 10.
  • On-site support: Pastor Philip, October 5; Jacqueline, October 6–7; Sinnie, October 8–9; Rose, October 9; Judy and Janet, October 9 (photos and on-site support). Jacqueline and Sinnie help with light duties only, with no heavy lifting. Ron directs installation; building access arrangements are to be confirmed separately.
  • Food and photos: Lily, October 5; Catherine, October 6; 霞姐, October 7 and 9 (food); Judy and Janet, October 9 (additional photos). Rose, Cecilia and Shiny provide a light meal on October 8. Amy prepares food for October 9 and delivers it after 6 pm (approx.); Adam also brings the food prepared by 霞姐 to church.
  • Cleanup: Peggy, Monday, October 5, and Saturday, October 10. Saturday cleanup follows construction, which is expected to stop around 8:30 pm, to prepare for Sunday worship. Her arrival time is to be confirmed. Leave the floor protection in place.
  • Daily crew target: Four build helpers each evening, in addition to Ron. Food, photos, cleanup and other support roles do not count toward this target.

Background: Sanctuary Rooms Build Team.

第四周 · 2026 年 10 月 26–30 日

同心建造,一步一步往前。

10 月 27 日:靠窗一侧的框架加固已完成。荣强弟兄与 Ken Fong(嘉辉)、Adam、Qiang Li(李强)和 Gabriel 一起施工;Catherine(牛慧)、涵之和 Pastor Julia黄传道 预备餐食。10 月 28 日计划安装剩余墙面石膏板。

状态:10 月 27 日(周二):荣强弟兄与 Ken Fong(嘉辉)、Adam、Qiang Li(李强)和 Gabriel 一起施工;Catherine(牛慧)、涵之和 Pastor Julia黄传道 预备餐食。靠窗一侧的框架加固已完成。10 月 28 日(周三):Roy 和邓集已确认协助荣强安装剩余墙面石膏板,还需要 1 位施工帮手;Vincent 和 Monica 预备餐食,由 Vincent 于下午四点多送达。10 月 29 日(周四):Roy、Qiang Li、Ken Fong、Adam 和邓集已确认,施工帮手人数已齐;简牧师预备餐食,Peggy 已确认清洁,清洁时间待确认。10 月 30 日(周五)休息,不安排施工或清洁。

最后更新:2026 年 10 月 27 日。

一起记得建造背后的盼望

在一项项工作中,愿我们记得:让年轻家庭照顾孩子时,仍能与会众一同敬拜;减少父母和祖辈抱着孩子上下楼的负担;也让不同事工共享空间。盼望我们把欢迎和关爱化为行动,跨代同行,一同敬拜。

中英双语图解:主堂两间房间,让年轻家庭继续参与崇拜,减少上下楼的需要,并供不同事工共享。
查看完整大图 · 点击图片可打开大图并放大阅读。

建设进度一览

10 月 27 日更新:靠窗一侧框架加固已完成。10 月 26 日开始安装墙面石膏板,当晚完成约一半;10 月 28 日计划安装剩余墙面石膏板,接缝及表面处理和油漆仍待完成。

已达到的里程碑

  • 房间木框架已搭起基本木框架已就位。
  • 外侧木板已刷好弟兄姊妹已预备好木板;外侧木板安装现已完成。
  • 已增设连接加固第二周已加装连接件,加强部分结构与墙面的连接。
  • 墙面最后加固已完成与墙面的最后加固已完成。
  • 外侧木板安装已完成已刷好外侧木板的安装已完成。
  • 两间房间天花板石膏板均已安装10 月 20 日安装第一间;10 月 21 日完成较困难的另一间。石膏板接缝及表面处理仍未完成。
  • 灯光开关已调低10 月 21 日:Alexander 回应 George(耀基)的建议,按无障碍要求调低灯光开关。
  • 隔音板已安装10 月 23 日:有了合适的切割工具,荣强弟兄、Adam、Ken(嘉辉)、Phoenix(小毛)和她的爸爸一起完成安装。
  • 靠窗一侧框架加固已完成10 月 27 日:完成靠窗一侧的框架加固,为安装剩余墙面石膏板作准备。

下一步 · 第四周安排

  • 墙面石膏板及其余工作10 月 28 日计划:靠窗一侧框架加固已完成,继续安装剩余墙面石膏板;具体分工由荣强确认。
  • 周四清洁 · 周五休息Peggy 已确认 10 月 29 日清洁,时间待确认;10 月 30 日不安排施工或清洁。

接下来要完成

  • 玻璃窗及门安装房间玻璃窗和门。
  • 通往门厅的新门洞开出计划中通往门厅的新门口。
  • 石膏板及油漆两间天花板及隔音板已安装,墙面石膏板正在安装中;剩余板材、接缝及表面处理和油漆仍待完成。
  • 灯具及开关灯光开关已按无障碍高度要求调低;其余灯具及开关工作仍待完成。
  • 通风设备安装通风设备,协调电源、气流及风管路线。
  • 电视及小音箱为家长及小组使用,安装电视和小音箱。
  • 影音网络及布线完成影音、网络连接及相关布线。

封墙前先协调:与相关有经验的帮手确认剩余电线、影音网络及通风路线。靠窗一侧框架加固已完成,10 月 28 日计划安装剩余墙面石膏板。以上是项目尚余工作,不代表承诺在第四周全部完成。

第四周 · 帮手报名岗位

第四周先列待确认安排:沿用除荣强以外 3 位施工帮手的目标,另按需要安排约 2–3 位实际支援人员。每天工作、时间和其余人员出席仍待确认,不自动沿用上周名单。

即使当晚人手已齐,愿意参与仍然欢迎。每天参与都是自愿的,可参与部分时段,也可轮替;请顾及家庭、团契及休息。

日期及时间工作重点已确认施工帮手实际支援待报名施工岗位
10 月 26 日(周一)下午 5:30–晚上 9:30工作重点:待确认:当天工作及合适分工由荣强确认。已确认帮手:Ken Fong(嘉辉)
施工帮手 · 具体分工由荣强安排
Qiang Li(李强)
施工帮手 · 具体分工由荣强安排
方健
施工帮手 · 具体分工由荣强安排
周磊
施工帮手 · 具体分工由荣强安排
实际支援:材料搬运/现场整理
待报名
现场支援
骏飞传道
餐食
Lily 师母 · 预备并送来晚饭
待报名岗位:人手已齐具体分工由荣强安排。
10 月 27 日(周二)实际参与记录工作重点:完成靠窗一侧的框架加固,为安装剩余墙面石膏板作准备。实际到场:Ken Fong(嘉辉)
施工帮手 · 已参与
Adam
施工帮手 · 已参与
Qiang Li(李强)
施工帮手 · 已参与
Gabriel
施工帮手 · 已参与
实际支援:餐食
Catherine(牛慧)、涵之和 Pastor Julia黄传道 · 预备餐食
待报名岗位:人手已齐已记录实际参与。
10 月 28 日(周三)开始及结束时间待确认工作重点:计划:靠窗一侧框架加固已完成,继续安装剩余墙面石膏板。已确认帮手:Roy
施工帮手 · 具体分工由荣强安排
邓集
施工帮手 · 具体分工由荣强安排
实际支援:材料搬运/现场整理
待报名
餐食
Vincent 和 Monica
Monica:排骨汤;Vincent:烤牛肉、烤鸡肉及面包。
Vincent 预计下午四点多送达。
待报名岗位:还差 1 位施工协助 · 1 位待报名;具体分工待确认
10 月 29 日(周四)开始及结束时间待确认工作重点:待确认:当天工作及合适分工由荣强确认。施工后清洁,时间待确认。已确认帮手:Roy
施工帮手 · 具体分工由荣强安排
Qiang Li(李强)
施工帮手 · 具体分工由荣强安排
Ken Fong(嘉辉)
施工帮手 · 具体分工由荣强安排
Adam
施工帮手 · 具体分工由荣强安排
邓集
施工帮手 · 具体分工由荣强安排
实际支援:材料搬运/现场整理
待报名
餐食
简牧师 · 预备餐食
周四清洁
Peggy · 时间待确认
待报名岗位:人手已齐具体分工由荣强安排。
10 月 30 日(周五)休息日 · 不安排工作工作重点:休息,不安排施工或清洁。已确认帮手:不适用实际支援:不安排待报名岗位:不适用 · 休息日

实际支援与施工人数分开。Peggy 已确认本周周四清洁,时间待确认;周五休息。欢迎轻量支援,不搬重物。

玻璃、电工、通风及结构工作需要合适且有经验的帮手。由荣强确认安全分工,开门安排另行确认。周末不安排施工。

每次开工前

  1. 逐日确认出席、开始及结束时间,以及开门锁门安排。
  2. 由荣强确认合适的工作、工具及当天工序;封墙前协调相关专门工作。
  3. 确认后才安排餐食及实际支援;轻量支援人员不搬重物。
  4. 地板保护继续保留,除非另有商定;Peggy 已确认 10 月 29 日(周四)清洁,时间待确认;10 月 30 日(周五)休息。

往周记录

以下保留之前的排班及参与记录;历史人手缺口不是目前招募需求。

第三周 · 10 月 19–23 日

历史排班及已报告参与记录。较早条目保留原记录的确认状态,不是第四周报名名单。下方记录周五隔音板安装、施工人员、清洁及餐食。由荣强带领;Phoenix(小毛)和她的爸爸回应了周四晚上的帮手呼吁。

日期及时间工作重点已确认施工帮手实际支援待报名施工岗位
10 月 19 日(周一)开始及结束时间待确认工作重点:George 专注完成与墙面的加固;荣强弟兄带领团队安装剩余已刷好的外侧木板。已确认帮手:George(耀基)
完成与墙面的加固
邓集
协助安装
17:30–21:00
Ken(嘉辉)
施工帮手 · 具体分工由荣强安排
实际支援:材料搬运/现场整理
骏飞传道
餐食预备
Dennis & Amy
Lily 师母
待报名岗位:人手已齐包括切板/材料预备在内的具体分工,由荣强确认。
10 月 20 日(周二)开始及结束时间待确认工作重点:墙面最后加固及外侧木板安装已完成;已安装一间房间的天花板石膏板。已确认帮手:Adam
施工帮手 · 具体分工由荣强安排
George(耀基)
施工帮手 · 具体分工由荣强安排
Ken(嘉辉)
施工帮手 · 具体分工由荣强安排
Gabriel
协助安装 · 已参与
实际支援:材料搬运/现场整理
可报名
餐食预备
Vincent & Monica
计划烤一些牛肉、猪排和鸡肉。
小食预备
霞姐 · 一份小食
待报名岗位:人手已齐工作包括切板/材料预备及协助安装,具体分工由荣强确认。
10 月 21 日(周三)开始及结束时间待确认工作重点:完成较困难的另一间房间天花板石膏板安装。Alexander 回应 George(耀基)的建议,按无障碍高度要求调低灯光开关。已确认帮手:邓集
协助安装
17:30–21:00
Adam
施工帮手 · 具体分工由荣强安排
Ken(嘉辉)
施工帮手 · 具体分工由荣强安排
Gabriel
协助安装
实际支援:厨房支援
Janet & Judy
加热饭菜,预备水果、沙拉及龙眼茶。
电气调整
Alexander
回应 George(耀基)的建议,按无障碍高度要求调低灯光开关。
晚餐
使用 10 月 20 日(周二)余下的饭菜。
待报名岗位:人手已齐工作包括切板/材料预备及协助安装,具体分工由荣强确认。
10 月 22 日(周四)开始及结束时间待确认工作重点:隔音施工有一些进展;切割隔音板仍需找到合适工具。实际到场:Adam
施工帮手 · 已到场
Jim Deng(邓集)
施工帮手 · 已到场
杜加坤弟兄
施工帮手 · 已到场
Ken(嘉辉)
施工帮手 · 已到场
实际支援:材料搬运/现场整理
可报名
餐食预备
Catherine(牛慧)
待报名岗位:人手已齐具体分工由荣强确认。
10 月 23 日(周五)实际参与记录实际工作:有了合适的切割工具,由荣强弟兄带领完成隔音板安装。实际到场:Adam
隔音板安装
Ken(嘉辉)
隔音板安装
Phoenix(小毛)
隔音板安装
Phoenix 的爸爸
隔音板安装
实际支援:清洁
Peggy & Ally
餐食预备
简牧师 · 为团队预备家常饭菜
施工人手:人手已齐
第二周 · 10 月 13–16 日

历史计划及岗位确认,包括周五实际参与记录;不是第三周报名名单。

状态: 第二周:周二、周三及周四施工人手已齐。周五实际施工及支援人员已记录在下方。Susan(晓英)周三现场支援;Catherine(牛慧)周四送餐及现场支援。周五清洁已完成,场地已为周六活动预备好。
最后更新: 2026 年 10 月 17 日。

第二周计划于 10 月 13 日至 16 日(周二至周五)施工,由谢荣强带领。周二晚上 5:30 开始,结束时间及其余晚上的时间待确认。这一阶段按岗位分工:除荣强以外,3 位施工帮手,另按需要安排约 2–3 位实际支援人员。即使当晚人手已齐,愿意参与的弟兄姊妹仍然欢迎;具体工作由荣强安排。每天参与都是自愿的,帮手可轮替,不需要每晚都来。

第二周施工时间及名单

日期及时间安排已确认施工岗位支援岗位待报名施工岗位
10 月 13 日(周二)
晚上 5:30 开始;结束待确认
安排:先加强框架及连接,再安装已刷好的外侧木板。门的工作由荣强按进度安排。已确认岗位:切板+预钻孔:
Adam 和 Gabriel
具体分配由荣强安排。
安装:
Ken Fong(嘉辉)
其他支援:Judy · 现场支援
Janet · 现场支援
Judy · 带一道菜
霞姐 · 带一道菜
待报名施工岗位:人手已齐
10 月 14 日(周三)
晚上;时间待确认
安排:先加强框架及连接,再安装已刷好的外侧木板。门的工作由荣强按进度安排。已确认岗位:切板+预钻孔:
Adam 和 Gabriel
预钻孔或安装:
邓集
切板、预钻孔及安装,3 位帮手的具体分工由荣强安排。
支援岗位:Susan(晓英) · 现场支援:搬运材料、清洁;到场时间待确认
按需要欢迎其他实际支援,合计约 2–3 位。
待报名施工岗位:人手已齐
10 月 15 日(周四)白天
上午 10:00 开门
安排:Sean 来布线;白天的安排与晚上施工分开。已确认岗位:Sean · 布线支援岗位:Ericson · 上午 10:00 到教会,为 Sean 开门待报名施工岗位:不适用——白天布线及开门安排
10 月 15 日(周四)
晚上;时间待确认
安排:先加强框架及连接,再安装已刷好的外侧木板。门的工作由荣强按进度安排。已确认岗位:切板:
Du Jiakun(杜弟兄)
预钻孔或安装:
邓集
安装:
Enoch Zheng(郑以诺)
合适工作及具体分工由荣强安排。
支援岗位:Catherine(牛慧) · 送餐
Catherine(牛慧) · 现场支援
材料搬运/现场整理 · 按需要可报名
清洁 · 按需要可报名
按需要合计约 2–3 位支援人员,岗位可兼任;到场时间待确认。
待报名施工岗位:人手已齐
10 月 16 日(周五)
实际参与记录
实际工作:继续加固及安装已刷好的外侧木板。George(耀基)和 Adam 配搭加装连接件、加强与墙面的连接,荣强带队安装外侧木板。大家一起清洁,为周六粤语崇拜及五饼二鱼预备好场地。实际到场:施工带领:
谢荣强
加固:
George(耀基)和 Adam
其他施工帮手:
Jacob(曲华)
Sarah(小滨)
Luke
Ken Fong(嘉辉)
实际支援:Ericson · 协助修好保安系统
Peggy · 现场清洁
添平和 Ally · 清扫及收集前门落叶
简牧师 · 下午较早到教会,为施工团队做饭
Yi Kiu(二娇) · 带来馅饼
大家一起收拾清洁,为周六粤语崇拜及五饼二鱼预备好场地。
施工人手:人手已齐

报名空缺岗位:请联系添平,说明日期、岗位和方便的时间,例如“周四——预钻孔”。请说明使用工具的经验或搬运限制,由荣强确认合适的分工并指导。施工和支援分开,支援岗位可兼任;出席确认后再更新名单。

第二周:岗位与配搭方式

  • 荣强——施工带领: 荣强负责量尺寸、作决定、安排顺序和安全,并在需要时亲自固定,提高施工效率。帮手按他的尺寸和指示配搭;并非每项工作都能重复照做。
  • 切板——1 位: 按荣强量好的尺寸切板,由他安排合适的人并指导;切板帮手可轮替。
  • 预钻孔——1 位: 按荣强指定的位置预钻孔,为下一步安装预备。
  • 固定/安装——1 位: 按荣强安排协助固定和安装;岗位可随当天工作调整。
  • 实际支援——按需要约 2–3 位: 搬运合适的材料、整理现场、清洁及鼓励团队。支援不计入 3 个施工岗位。Jacqueline、Sinnie 等轻量支援人员若参与,不安排搬重物。
  • 已确认 10 月 13 日(周二): Adam 和 Gabriel 协助切板及预钻孔,具体分配由荣强安排。Ken Fong(嘉辉)协助荣强安装。Judy 和 Janet 现场支援,Judy 和霞姐各带一道菜。
  • 已确认 10 月 14 日(周三): Adam 和 Gabriel 加入切板/预钻孔,邓集协助预钻孔或安装。3 位施工帮手人手已齐,具体岗位分配由荣强安排。Susan(晓英)协助现场支援,包括搬运材料及清洁;到场时间待确认。
  • 10 月 15 日(周四)白天开门: Ericson 上午 10:00 到教会,为 Sean 开门布线,与晚上的施工分开。
  • 已确认 10 月 15 日(周四): Du Jiakun(杜弟兄)切板;邓集协助预钻孔或安装;Enoch Zheng(郑以诺)协助安装。3 位施工帮手人手已齐,合适工作及具体分工由荣强安排。Catherine(牛慧)送餐及现场支援。到场时间待确认,其他实际支援按需要仍可报名。以上只确认所列日期。
  • 10 月 16 日(周五)实际参与: 荣强带队安装外侧木板;George(耀基)和 Adam 配搭加固。Jacob(曲华)、Sarah(小滨)、Luke 和 Ken Fong(嘉辉)也到场帮忙。Ericson 协助修好保安系统。Peggy 清洁现场,添平和 Ally 清扫及收集前门落叶。简牧师下午较早到教会,为施工团队做饭;Yi Kiu(二娇)带来馅饼。大家一起收拾清洁,场地已为周六粤语崇拜及五饼二鱼预备好。

施工顺序与时间预期

  • 先加固,再完成房间外侧: 先加强框架及连接,再安装之前已刷好的外侧木板。按进度处理门的工作;荣强提到的两个门洞,具体范围由他确认。
  • 电工是后续工作的前提: 电工团队的时间不由荣强直接掌握。封闭内侧墙面前,要协调电工进度及所需施工空间。
  • 之后完成室内: 电工完成后,再进行内侧板材/石膏板、表面处理及油漆;具体工序由荣强确认。
  • 估计,不是完工承诺: 荣强估计整体可能还需约两周,其中电工完成后,室内收尾约需一周。实际日期取决于电工进度和现场工作;留足时间,把工作做好。
  • 周五清洁与周末活动: 10 月 16 日(周五)大家一起收拾清洁,场地已为周六粤语崇拜及五饼二鱼预备好。周六尚未安排施工,如需做工须另行协调教会活动。10 月 18 日(主日)休息。
  • 感恩节休息: 10 月 11 日(主日)及 12 日(周一)不施工,周二恢复。

年轻人写经文——另行协调

荣强原则上同意年轻人在内侧框架封板前,用记号笔在获准的位置写经文,并拍照留念。具体位置和时间须与荣强协调。参与者须有人带领,在与危险施工分开的安全区域进行。活动时间尚未安排。

第二周每次开工前

  1. 逐日确认出席和岗位,不自动沿用上周的可用时间。
  2. 荣强确认工作、尺寸、材料工具及安全分工;封闭内侧前,协调电工施工空间。
  3. 确认结束时间、周三至周五开始时间,以及开门锁门安排;支援人员不自动承担开门责任。
  4. 实际支援、食物和拍照须有人确认才安排;支援与施工人数分开,并保留不搬重物等限制。
  5. 周五为周六活动预备的清洁已完成。地板保护继续保留,除非另有商定。
  6. 在封板前,与荣强安全协调年轻人写经文的机会。
第一周 · 10 月 4–10 日

第一周存档——10 月 4 日至 10 日

以下保留上周已确认的排班供参考。当时目标为除荣强以外 4 位帮手;历史缺口不是当前招募需求。

日期及时间安排已确认帮手其他支援还需要
10 月 4 日(主日)
下午 2:00
安排:荣强采购材料,Frank 协助采购,方健协助装卸。已确认帮手:Frank(采购支援)
方健 Jim Fang(装卸)
其他支援:—还需要:人手已齐
10 月 5 日(周一)
晚上 5:30–9:30
安排:安装施工,荣强带领已确认帮手:嘉辉
Phoenix (小毛)
Phoenix 的爸爸
其他支援:Pastor Philip · 现场支援
Lily · 茶点、拍照
Peggy · 清洁(时间待确认)
还需要:还差 1 位
10 月 6 日(周二)
晚上 5:30–9:30
安排:安装施工,荣强带领已确认帮手:Adam · 工程/结构承重检查
嘉辉
李强
Alex Chan
骏飞传道
其他支援:Catherine · 送吃的、照相
Jacqueline · 轻量支援(不搬重物)
还需要:人手已齐
10 月 7 日(周三)
晚上 5:30–9:30
安排:安装施工,荣强带领已确认帮手:Adam · 工程/结构承重检查
嘉辉
邓集
Bin Yang 杨滨
其他支援:Jacqueline · 轻量支援(不搬重物)
霞姐 · 食物
还需要:人手已齐
10 月 8 日(周四)
晚上 5:30–9:30
安排:安装施工,荣强带领已确认帮手:Adam · 工程/结构承重检查
嘉辉
邓集
James
Enoch
Tim
Nikki
Joanne
David Chan
其他支援:Sinnie · 轻量支援(不搬重物)
Rose · 简餐
Cecilia · 简餐
Shiny · 简餐
还需要:人手已齐
10 月 9 日(周五)
晚上 5:30–9:30
安排:安装施工,荣强带领已确认帮手:Adam · 工程/结构承重检查
嘉辉
David Chan
Enoch
Sarah(小滨)
其他支援:Sinnie · 轻量支援(不搬重物)
Rose · 现场支援
霞姐 · 食物(Adam 带到教会)
Amy · 食物,约六点多送到教会
Judy · 额外拍照及现场支援
Janet · 额外拍照及现场支援
还需要:人手已齐
10 月 10 日(周六)
下午 4:30 至晚上 9:30
安排:继续安装施工,荣强带领。预计晚上 8:30 左右停止施工,随后清洁,为主日敬拜预备。地板保护继续保留,不拆掉。已确认帮手:Frank
Lei Zhou(周磊)
Jim Fang(方健)
Enoch
Sarah(小滨)
其他支援:Peggy · 施工后清洁(到场时间待确认)还需要:人手已齐

第一周人员与分工

  • 安装负责人:荣强。他指挥施工,并决定每晚哪些工作可以安全进行。
  • 工程:Adam,10 月 6 日至 9 日。主要与荣强一起检查结构支撑及承重方面的事项。
  • 已确认的施工帮手:嘉辉,10 月 5 日至 9 日;李强、Alex Chan 和骏飞传道,10 月 6 日;邓集,10 月 7、8 日;Bin Yang 杨滨,10 月 7 日;David Chan,10 月 8、9 日;James,10 月 8 日;Phoenix (小毛) 和 Phoenix 的爸爸,10 月 5 日;Enoch,10 月 8 日至 10 日;Tim、Nikki 和 Joanne,10 月 8 日;Sarah(小滨),10 月 9、10 日;Frank、Lei Zhou(周磊)和 Jim Fang(方健),10 月 10 日。
  • 现场支援:Pastor Philip,10 月 5 日;Jacqueline,10 月 6、7 日;Sinnie,10 月 8、9 日;Rose,10 月 9 日;Judy 和 Janet,10 月 9 日(拍照及现场支援)。Jacqueline 和 Sinnie 协助轻量工作,不搬重物。安装工作由荣强指挥;开门安排另行确认。
  • 食物及拍照:Lily,10 月 5 日;Catherine,10 月 6 日;霞姐,10 月 7、9 日(食物);Judy 和 Janet,10 月 9 日(额外拍照支援)。Rose、Cecilia 和 Shiny 于 10 月 8 日提供简餐。Amy 于 10 月 9 日准备食物,约六点多送到教会;Adam 也会将霞姐预备的食物带到教会。
  • 清洁:Peggy 于 10 月 5 日(周一)及 10 月 10 日(周六)协助清洁。周六预计晚上 8:30 左右停止施工,随后清洁,为主日敬拜预备。她的到场时间待确认。地板保护继续保留,不拆掉。
  • 每晚人数:除荣强以外,目标是每晚 4 位施工帮手;更多帮手可轮替休息。食物、拍照、清洁及其他支援岗位不计入此人数。

背景:主堂房间施工团队.